Navigation: Production > Capacity Planning: APS No contents entries on this page Contents beas provides a complete Advanced Planning & Scheduling system.
Overview of functions • Order-oriented view • Resource or operation oriented view • Planning at production order level or operation level • Consideration of data from beas work orders • Integration of MS-Project and APS • Scheduling and optimization of manufacturing processes • Flexible calculation methods • Flexible views and groupings
The APS module has been fully integrated into BEAS. The heart of APS – capacity planning – is used by the standard program (backward scheduling) as well as by MRP, Pool Administration and all other relevant program components equally. A change in the APS has a direct effect on production order management and pool management and also directly on MRP. All information is always available online. The information from FDC and MDE is available directly in the APS. Both rough and detailed planning is possible. Once a work order is roughly scheduled by beas, that means if an work order BOM and routings are available, the processing can be done with APS.
The orientation is user-definable – whether resource-oriented, order-oriented, project-oriented or by employee, material, production line, location-specifically or separately for detailed machine planning or the management of laborers, whether rough planning at production order level or detailed planning as far as individual machine planning accurate to the minute. The APS supports any priority control including user-definable nesting, tool management, user-definable multi-machine and multi-order operation, parallel processing and overlaps. Material requirements planning works directly with APS. APS is preconfigured for rapid familiarization.
The main task of APS (advanced planning & scheduling) is to support an optimal planning of production in the company.
The APS module is fully integrated into beas. The core is the capacity planning, it is accessed by the MRP, the pool management and all other relevant parts of the program.
For detailed planning the following functions are available:
Order oriented view Resource oriented view Planning on work order level Planning on operation level Flexible calculation methods Flexible views and groupings
The production planning is always done with the actual production data. There is no copy of the data generated for planning. Any change takes immediate effect in the production. If mistakenly a wrong action is carried out, there is a powerful Undo function available.
Prerequisite for the correct use of the ASP is the correct settings of various parameters. These include:
Resources Business calendar Work orders Calculation types
Activation and License
To activate the APS, license must be assigned to the respective computer. Before this has not been done, you have no access to certain settings. To assign a license open the following menu item:
Administration - License
With the icon next to the APS licenses, you can assign them. With the button New you add a new user / computer.
linktraining Training unit APS