RN PI Planning Recommendations - larralapid/finds GitHub Wiki
Lightweight PI Planning Approach for RN1.5
Pre-Planning (2 Days)
Day 1: Readiness Review
-
Product Vision Session (2 hours)
- CPO presents overall product direction
- Engineering leads share technical vision/constraints
- Open discussion on challenges/opportunities
- Outcome: Shared understanding of direction
-
Capacity Planning (2 hours)
- Engineering presents team capacity model
- Review historical velocity data
- Factor in maintenance/support overhead
- Outcome: Agreed capacity guardrails
Day 2: Feature Review
-
Feature Walkthrough (3 hours)
- PMs present high-level features
- Engineering asks clarifying questions
- Architecture team shares technical considerations
- Outcome: Initial feature understanding
-
T-Shirt Sizing Workshop (2 hours)
- Cross-functional teams size features
- Use planning poker for alignment
- Document key assumptions
- Outcome: Rough feature estimates
PI Planning (2 Days)
Day 1: Planning
-
Opening (1 hour)
- Review planning objectives
- Present business context
- Share known risks/dependencies
-
Team Breakouts (4 hours)
- Teams work on sprint plans
- POs available for questions
- Architecture team for technical guidance
- Focus on first 2 sprints in detail
-
Draft Plan Review (2 hours)
- Teams present draft plans
- Identify cross-team dependencies
- Highlight risks and assumptions
- Get feedback from stakeholders
Day 2: Finalization
-
Risk/ROI Analysis (2 hours)
- Review risks vs business value
- Prioritize based on ROI
- Make scope trade-off decisions
- Document key assumptions
-
Plan Finalization (3 hours)
- Teams adjust based on feedback
- Finalize sprint assignments
- Lock in key milestones
- Agree on delivery risks
-
Confidence Vote (1 hour)
- Teams vote on confidence
- Address major concerns
- Get leadership buy-in
- Formal plan commitment
Trust-Building Elements
Psychological Safety
- No blame for estimation misses
- Focus on learning from past releases
- Encourage open sharing of concerns
- Create safe space for questions
Transparency
- Share all planning artifacts openly
- Make assumptions explicit
- Clear escalation paths
- Regular progress visibility
Shared Ownership
- Joint decision-making
- Collective problem-solving
- Balanced PM/Engineering input
- Mutual accountability
Clear Boundaries
- Respect for team capacity
- Change management process
- Escalation guidelines
- Support commitment
Follow-up
Week 1
- Daily cross-team standups
- Dependency resolution
- Risk mitigation planning
- Quick feedback loops
Weekly
- Plan vs actual review
- Impediment removal
- Dependency check
- Risk reassessment
Monthly
- Feature progress review
- Capacity utilization check
- Process improvement
- Trust metric review
Success Metrics
Delivery
- Predictability score
- Scope stability
- Risk retirement rate
- Milestone achievement
Team Health
- Trust assessment
- Collaboration rating
- Psychological safety
- Team satisfaction
Process
- Planning effectiveness
- Communication quality
- Decision latency
- Impediment resolution