Sprint capacity is not used by this group to limit points in a sprint, but to track work throughput via a burndown chart.
The values applied to tickets can be found in the announce channel on our teams instance. The points for a ticket should include time for reviews and any rework and reviews that may be needed. At the last update of this page these are:
1 point < 1 hour
2 points < 0.5 day
3 points < 1 day
5 points < 2 days
8 points < 3 days
13 points < 5 days
20 points < 8 days
40 points < 16 days
Timeboxes - pointing allows for reviews
0.5 day - 3 points
1 to 1.5 days - 5 points
2 to 2.5 days - 8 points
3 to 4.5 days - 13 points
5 to 7 days - 20 points
The value assigned to a sprint is the_number_of_days_in_this_sprint * the_average_from_the_previous_three_sprints_of_(points_completed_in_sprint/the_number_of_days_in_the_sprint)
The number of days in a sprint is the sum of the days that the team members are available between the start and end date, with a multiplier to allow for the time spent not doing work on tickets which varies based on the responsibilities of different team members.