Project Timeline - se701g2/Doto GitHub Wiki

Overview of Project Timeline

The following is a list of milestones/features with their expected dates of completion. The features listed aren't exhaustive and can change at any time.

Milestone 1 - Initial setup and preparation - 9/03/2020

  • Create a Github repository and add base project setup
  • Choose a licence
  • Assign all 22 group members to different parts of the tech stack
  • Set up Linting rules
  • Define code of conduct
  • Set up Slack for communication

Milestone 2 - Create base prototype for application - 13/03/2020

  • Able to add a task
  • Set up the database to track added tasks
  • Basic front-end UI set up
  • Add labels and end-dates to tasks
  • Able to choose task priorities
  • Server set up so that application isn't local

Milestone 3 - to be decided...