Project Timeline - se701g2/Doto GitHub Wiki
Overview of Project Timeline
The following is a list of milestones/features with their expected dates of completion. The features listed aren't exhaustive and can change at any time.
Milestone 1 - Initial setup and preparation - 9/03/2020
- Create a Github repository and add base project setup
- Choose a licence
- Assign all 22 group members to different parts of the tech stack
- Set up Linting rules
- Define code of conduct
- Set up Slack for communication
Milestone 2 - Create base prototype for application - 13/03/2020
- Able to add a task
- Set up the database to track added tasks
- Basic front-end UI set up
- Add labels and end-dates to tasks
- Able to choose task priorities
- Server set up so that application isn't local