RN1.4 UAT PM Connect Notes ‐ 15 JAN - sanjaygupta-professional/BDM GitHub Wiki
Executive Summary
The meeting focused on critical defect management and release readiness for Release 1.4, revealing significant challenges with defect tracking, categorization, and cross-team coordination. A substantial number of new defects were logged in the past 24 hours, requiring immediate attention and process alignment.
Key Updates & Status
Defect Status
- Total active defects: ~74 (across multiple tracking boards)
- New defects logged yesterday: ~40
- Critical/High/Medium defects targeted for resolution by next day
- Approximately 20 additional defects pending logging from Pablo's review
- Current regression testing completion: ~50%
Documentation & Tracking Challenges
-
Multiple tracking systems in place:
- UAT defect board (~94 UAT defects)
- Main release board (~74 active defects)
- Separate regression testing spreadsheet (limited access)
-
Process Issues:
- Unclear/Inconsistent defect categorization criteria
- Duplicate defects potentially present
- Unclear ownership of defect triage
- Communication gaps between QA and Product teams
Critical Decisions & Actions
Immediate Actions (Next 24 Hours)
-
Product Team:
- Yanick to log ~20 pending defects from Pablo's review - DONE
- Ben/Yanick to review defect categorization and priorities
- Remove PO tags from resolved items
- Team members to check emails and respond to pending comments
-
QA Team Needs To:
- Remove duplicate defects
- Share formal categorization criteria
- Clarify regression testing status and plan
Process Improvements
-
Documentation:
- Consolidate tracking to the single dashboard view
- Implement clear severity criteria:
- Critical: Data and insights/upload related
- High: Wrong UX implementation
- Medium: Existing workaround but annoying
- Low: UI alignment issues
-
Communication:
- Establish daily status updates
- Use one centralized dashboard for discussions
- Improve cross-team visibility
Risk Areas
- Release Timeline:
- Significant number of open defects
- Regression testing is only 50% complete
Next Steps
-
Engineering Meeting Preparation:
- Present complete defect count and status
- Discuss the feasibility of closing Critical/High/Medium defects by tomorrow
- Align on regression testing completion criteria
-
Process Implementation:
- Establish a single source of truth for defect tracking
- Implement clear categorization criteria
- Set up daily status review cadence