Production > Work order general > Work order document > WO document items > Edit work order item > Routing tab > Production routing > General_opsequ - robinfeng/beashelp GitHub Wiki

常规工序


Navigation: Production > Work order general > Work order document > WO document items > Edit Work Order Item > Routing tab > Production Routing: General No contents entries on this page Contents Work order item Edit work order item
Operation MS-Project Routing Edit routing External operation General Costs Scheduling Extended Tool Utilities Parallel Alternative Attachments

Field Meaning Setup for calculation The setup time in hours or minutes is taken into account in production and costing analysis as well as in precalculation See Setup for calculation This setting has an effect on calculation of target time
Setup for Sched+Cap. The set-up for sched+cap. in hours or minutes is considered in capacity planning and throughput time calculation. This setting has an effect on calculation of target time Mach+Labor Time/unit Secondary time Machine time/unit The actual processing time per work step and the cost element. See Mach+Labor Time/unit, Cost element, Time types Personnel costs on Cost Element Select cost type, to which personnel costs are booked Times per .. Finished items Number of assemblies finished in the time specified. For 100, the time specified refers to "per 100 assembly components per consumption unit". The default can be stored in the options. Times in … Unit of time in which times are stored – hours or minutes. The default can be stored in the options. Resource allocation Here you can specify the extent to which a resource can be utilized. See Resource allocation Operation active It can be set here whether the operation should be included. See Operation active This switch is hidden by default and can be activated via Confguration wizard Use factor The use factor – the inverse of work steps. Example: By sawing a board apart, the material is provided for two finished goods - the utility factor is thus 2. This setting has an effect on calculation of target time Work steps The opposite to the use factor. Example: Two steps are necessary to produce a part. The time per 1 cut is stored, the quantity of the required cuts is stored with number. This setting has an effect on calculation of target time Idle Time The idle time determines the time in hours, in which the semi-finished part must not be further processed. See Idle time Overlap Limit The overlap time to the next operation in hours.

0 enter number of hours 0 = No overlap limit -1 = parallel processing = following operation starts simultaneously with the current operation

see Overlap limit Parallel Operations and Overlapping Scrap Factor Scrap factor relating to this routing position in % This is calculated as (Mach+Labor time/unit) * (1 + scrap factor : 100) QC inspection plan A QC inspection plan can be stored for the position. See Routing QC-inspection plan

back to external operation op.sequ.