Production > Work order general > Work order document > WO document items > Edit work order item > Routing tab > Production routing > Costs_opsequ - robinfeng/beashelp GitHub Wiki

成本工序


Work order item Edit work order item
Operation MS-Project Routing Edit routing External operation General Costs Scheduling Extended Tool Utilities Parallel Alternative Attachments

For job time and the personnel cost rate you can enter marginal costs, full costs and cost types at full and marginal costs. Costs are plan costs (pre-calculation values) from the moment the work order or pre-calculation was created. Order time receipts are created always at current resource costs.

By default, this tab is hidden. It is visible only, if activated in Configuration wizard

see Resource costs

back to external operation op.sequ.