Production > Capacity planning > APS > Work with APS > Transit time and idle time - robinfeng/beashelp GitHub Wiki
Navigation: Production > Capacity Planning > APS > Work with APS: Transit time and idle time No contents entries on this page Contents Configuration of operation sequence
|--- Transit time --| |-- Planned time --| |--- Idle time--|
First operation has no transit time. Example with 2 operations
Plan time operation 1 Idle time operation 1 Transit time of resource of operation 1 Plan time operation 2 Idle time operation 2
Transit time can be used to expand lead times. In this way, urgent work orders can be squeezed in by reducing transit times in APS-calculation types or Priorities
In case of overlapping, always the largest transit time is used. The factory calendar is considered only, if this was enabled in Configuration wizard.
Overlapping
In case of overlapping the largest transit time is determined: hmtoggle_plus1 Example
Operation sequences 1,2 and 3 are parallel: 2 hours each, A2 has a transit time of 2 hours. Operation 4 is normal with 2 hours duration
A1 Start 8:00 - 12:00 A2 Start 8:00 - 12:00 A3 Start 8:00 - 12:00 Idle time A2: 12:00 - 14:00 A4 Start 14:00 - 16:00