Production > Capacity planning > APS > Work with APS > Scheduling - robinfeng/beashelp GitHub Wiki

排程


Navigation: Production > Capacity Planning > APS > Work with APS: Scheduling No contents entries on this page Contents This chapter describes how the lead time is calculated:

Delivery Date If a production order is created from a customer order, the delivery time is considered first. The delivery time is the time between production order delivery date and customer order delivery date and is defined in the settings.

Customer order delivery date Scheduled in the customer order. Work order delivery date Defined in the production position, generally delivery date of customer order minus x workdays at time y. Both can be configured. End time Calculated completion date Start Time Calculated start date Start date Calculated or manually specified start date

Structural processing

The structural calculation is shown in this example: The "Endproductonord" assembly consists of "subitemiionorder" and "subitemionorder"

durchlauf0 Production structure view

Before "Endproduct" can be started, the two subcomponents must be processed.

durchlauf1 APS view, lines minimized – forward-scheduled

It can clearly be seen here that in the time line work sequences 20 and 30 are started first and the upper assembly "Endproductonord" is only started when the assembly with the longer throughput time is ready. Forward scheduling always works in a resource-oriented way here, i.e. earliest possible start

Conversely, backward scheduling durchlauf2 APS view, lines minimized – backward scheduling.

In backward scheduling you start as late as possible (start 7 April). It can clearly be seen that assembly 30 starts later than assembly 20.

Position

The timeline of a work sequence consists of multiple parts.

Transfer Time Plan time - reported time Idle Time |----------------------------|--------------------------------------------------------|-----------------------| Start Time End time

Times for the resource are only reserved in the time between the start and end times. Closed work sequences are not calculated. Active logins are not considered.

Calculation of target time see Calculation of target time

The next operation is dependent on the overlap time, i.e. the next operation starts on transfer time + overlap time + idle time excluding plan time (graphical view for forward scheduling only):

Afo 1 Transfer time Plan time - reported time Idle Time |----------------------------|--------------------------------------------------------|-----------------------| |------ Overlap limit ----|---- Idle time---|--> Next operation

Transferred times are specified in Resource under Resource -> Planning -> Transfer Time in Days orResources -> Planning -> Transfer Times . Using the priorities, the idle time and the transfer time can be influenced.

help-achtung.zoom69Special feature: overlap and transfer time If the following routing position is overlapping or parallel, the transfer time does not apply to the following routing position, but rather to the routing position that is no longer defined as overlapping or parallel to this routing position.

help-achtung.zoom69Special feature: backward scheduling Certain functions such as firming and material requirements inspection are not available and do not work in a resource-optimized way. Overlaps are supported but are not displayed correctly graphically Backward scheduling supports no detailed planning. Instead, it uses a "daily pot for a resource", that means upon check of existing dispatches from other work orders only the time, but not the point in time (start) is checked.


返回 主页

⚠️ **GitHub.com Fallback** ⚠️