Resources Field Meaning Enable resource scheduling Option is visible only, if in Compute lead time for assemblies was enabled. Furthermore, Forecast - Gross calculation must be deactivated. If it was enabled, it will be disabled automatically when activating resource scheduling. With this option, not only material requirement will be computed, but also the required resources for a scenario. The computation time can be longer. Results can be viewed in order recommendation screen using the button "resources".