工具
Navigation: Inventory > Routing > Edit routing > Routing positions > Edit routing positions: Tool No contents entries on this page Contents The tools required for the operation can be defined in the Tool tab.
Operation catalog - Routing - Production routing - Calculation Edit routing External operation General Extended Tools Utilities Parallel Alternative Documents Special functions Field description of the tool position Field Meaning Position Consecutive number, but not a primary key. The list output is sorted by this number. Tool Tool key (selection from master data / tools) Active Checked, if entry is active Description Designation of the tool (cannot be changed) Determines lead time If checked, entry determines lead time. Setup time setup time Machine / operation time per unit Job time
(Previously Resources tab, in which tools, alternative work sequences, and parallel work sequences were listed in a table) A second row of buttons has been inserted here now. The top row of buttons relates to the tool list. Care should be taken here during processing.
General tab Field Meaning Drawing Number "Drawing number" field from the tool entry. Info Any information on the tool entry
Planning tab This tab is only active if a tool has been selected that has capacity planning. Field Meaning Idle Time Defines the time in hours after which the tool can no longer be used for other work orders (e.g. cooling, quality control, maintenance, etc.) Next work sequence begins after idle time If activated, the next work sequence can only be started after the idle time. Example: If the tool is a bin and this must be cooled before the finished product can be removed from the bin, the next work sequence can only be started after cooling. However if the idle time is for quality control of a tool, you can begin with the next work sequence immediately (i.e. switch deactivated)
Default Time tab This tab is only active if the tool defines the throughput time. If this tool is activated (only one tool can ever be activated which defines the throughput time), its throughput time information is copied to the operation.
Note Only fields are considered where entries have been stored in the tool. That why, you can remove all entries. Work step and use factor are only used if >0.
Example: Setup time of tool = nothing entered Processing time in tool = 5 mins Setup time is not changed in operation, thus it comes from tool.
Please make sure that you work the same way for all tools.
If a tool is activated, which determined the time, at saving it is transferred automatically to the operation.
Field Meaning Setup time Time for the setup process. Time specified per "Time per" Processing time The processing time for a unit of quantity per "Time per" in consumption unit per "Quantity per" finished parts. Info: Secondary processing times cannot be specified here. Quantity per .. Defines the number of finished parts in consumption units to which the processing time refers, e.g. 10 minutes per 1000 kg. Time by Defines whether times are specified in hours or minutes Number Number of required work steps e.g. 10 work steps in "processing time" are required Utility Utility factor, e.g. 10 units are produced at once per step or hub and per processing time. Cost element Accumulated costs are written to this cost element.
general settings on tools: See: Tool administration