Navigation: Inventory > Item structure > Item structure right click menu: Compute resources No contents entries on this page Contents In this screen, the material and resource requirement and the replenishment time can be calculated in advance for an assembly:
If great amounts are included in forecasts, using this advance calculation the MRP computation time can be reduced significantly. See MRP - Planning scenarios - Detail - Forecasts The result can be used in own reports. Results are saved in tables BEAS_OITM_MATERIAL BEAS_OITM_RESOURCEN if the option "Calculate material and resources" has been enabled.
Which assemblies to calculate can be selected with filters on item, item group etc using a (AND)-conjunction
Note Phantom assemblies are not considered in selection. If the sub-structure contains a sub-assembly, it will be broken down and taken into account.
Function Description Item from Selection filter Item to Selection filter Item group additional filter item group Item property additional filter item property Clerk additional filter clerk Calculate lead time Enabled: lead time is calculated based on the stored routing of the complete work order structure. The result is entered into the field "lead time"
See item master - planning data
Lead time is calculated as follows: backward scheduling from the moment of calculating the manufacturing lot size. The result is a date in the past. Then the number of days until the current day is calculated. The sum equals the lead time per manufacturing lot size. Calculate material and resources Enabled: material requirement and resource requirement is calculated
based on the stored routing of the complete work order structure related to the manufacturing lot size. The required material and resource times is calculated for the complete production.
The result is saved to the following tables: BEAS_OITM_MATERIAL BEAS_OITM_RESOURCEN
Quantities and times are stored scaled down per quantity unit.
Note: Material requirement of the purchase parts and storage related assemblies is saved. The requirement of order related assemblies is not saved, as these are neutral for balance calculation.
To perform the computation on a regular basis, you can create an activity.
See lead time and material requirement calculation Item structure right click menu MRP wizard MRP - planning scenarios - Details - Forecasts