Roll Call done by Subhash. Quorum not achieved. Short of 1 member. Bob Lockhart joins, quorum achieved.

Agenda

  1. Review of 1.2 items
  2. Status of 1.3 Items
  3. Interop

Tim moves that we approve agenda, Kiran seconds. Hearing no objections/abstentions, agenda is approved.

Prior meeting notes with updates posted by Saikat. Tim moves, Sue seconds. Meeting Minutes approved.

Minutes of meeting in wiki better to manage centrally an update in a central location. Issue of preventing updates to approved minutes. Subhash: Let us see for next few months on how it goes and make a decision if we have any issues

Status 1.2 Documents

  1. Document submitted to OASIS.
  2. Documents are currently sitting in queue behind PKCS#TC documents for OASIS review.

Status of 1.3 Items

1. Add a new column on wiki project pipeline when the proposals can be presented for each item.

Discussion about query enhancements with RNG

1. Kiran: Query enhancement along with RNG work with Tim underway. Need two weeks to wrap up and present to TC. 1. Kiran: Assumption: Server has only one RNG implementation. 1. John L: Is the returned RNG algorithm an enumeration of server's all RNG capability? Sometimes server may have a different RNG for certain operations. 1. Bob L. what happens when the server does not know the RNG used during key creation specifically when a key was registered? What would server return? Sometimes clients may not be sophisticated to know which RNG was used to generate a key? 1. John/Saikat: Server implementation may indeed have multiple RNG or combine them. Certain RNGs need to be used in certain situations. 1. Bob L.: Each managed object may have an additional attribute to indicate which RNG was used to create it? 1. Subhash: It seems there are two distinct tasks in Query enhancements. One client to request server capabilities. The other is which RNG per crypto managed object 1. ACTION: Subhash to create two independent tasks 1. John: getRandom. Actually seeding is more important than algorithm. Subhash requests John to create a proposal to capture this.

Interop

1. Tony: Interop sub committee formed. 1. Tony: Informal Interop test starts in mid December 1. Tony: Formal Interop test starts in January with members 1. Tony: Statement of use documents from participating members like prior Interop tests. 1. Peter: EMC/RSA is not participating but I would be interested to know the interop status and updates.

Next KMIP TC call

1. Considering Thanksgiving holiday and no agenda for next week's call, TC call for next two weeks cancelled. Next KMIP weekly call on December 5th.

Review of pipeline

Tim to update the project pipeline. Query enhancement proposal after two weeks hiatus.

Tim moves that we adjourn, Sue seconds. Hearing no objections/abstentions, we are adjourned.