Project Planning - moria0525/App_matnas GitHub Wiki

Date Task status
21.9.16 Meeting #1 with client Completed
13.10.16 Meeting #1 with Mr.Roger Cohen Completed
24.10.16 Iteation 0 - Starting Completed
3.11.16 Meeting #2 with client - create list of Requirements Completed
4.12.16 submit Report Proposition Completed
5.12.16 downloaded 'Android Studio' Completed
5.12.16-1.2.17 build prototype Completed
16.1.17 Meeting #2 with Mr.Roger Cohen - prototype Completed
18.1.17 Meeting #3 with client - prototype Completed
1-11.2.17 repair prototype, report and create video Completed
12.2.17 submit Report Prototype Completed
12.2-1.4.17 development Completed
in Mail Meeting with Mr.Roger Cohen Completed
3.4.17 Meeting #4 with client Completed
4.5.17 submit Report Construction Completed
4.5-1.6.17 deployment - con Completed
11.6.17 Meeting #5 with client Completed
in Mail Meeting with Mr.Roger Cohen Completed
21.6.17 submit Report Final Completed
21.6.17 Video Video Completed
2.7.17 test Completed