Sprint Schedule - mhmunem/Grocery-Comparison-App GitHub Wiki

Resource and Duration Overview:
  • Team size: 6 people
  • Hours per person per week: 32 hours
  • Total hours per week (6 people): 192 hours

Sprint Schedule

Sprints Overview
  • Sprint 0: Setup (1 week)
  • Sprint 1 - 4: Development (2 weeks each)
Sprint 0: Setup
  • Duration: 1 week
  • Dates: December 2, 2024 – December 11, 2024
Sprints 1–4: Development
  • Duration: 2 weeks each

  • Sprint 1: December 11, 2024 – December 25, 2024

  • Sprint 2: December 25, 2024 – January 8, 2025

  • Sprint 3: January 8, 2025 – January 22, 2025

  • Sprint 4: January 22, 2025 – February 5, 2025

  • Total Project Hours per Sprint:

    • Sprint 0: 192 hours
    • Sprint 1: 384 hours
    • Sprint 2: 384 hours
    • Sprint 3: 384 hours
    • Sprint 4: 384 hours
    • Total project time: 1728 hours