First Iteration

The first set of sprints was completed by bhavicp and hamstar during the final semester of the AUT Project Paper. They did six two week sprints following this process.

  • Sprint 1: 13th August 2012 - 24th August 2012
  • Sprint 2: 27th August 2012 - 7th September 2012
  • Sprint 3: 10th September 2012 - 21st September 2012
  • Sprint 4: 24th September 2012 - 5th October 2012
  • Sprint 5: 8th October 2012 - 19th October 2012
  • Sprint 6: 22nd October 2012 - 2nd November 2012