Week 6 Iteration Plan - djgamekid/GDP-Group-I-bearcatmanager GitHub Wiki
What tasks from the previous iteration plan did not get completed?
- Linking the Database to the Ticket Generation
- Adding Logic to add Different Entities to the DB
- Events pulled down into (iOS)app
- Password reset functionality(User)
- Display featured events(iOS)
Why did they not get completed?
- Getting errors while connecting to the Database for Ticket Generation in the Web application
- Functions were not properly implemented which delayed components from being installed
- Waiting on Admin functionality to be added to implement the user functionality
Which tasks from the previous iteration plan will you move to this current plan?
- Web App designs
- Backend CRUD operations to Frontend
- Admin page navigation and design
- Events pulled down into (iOS)app
- Password reset functionality(User)
- Display featured events(iOS)
An assignment of tasks to each group member with a concrete plan for demonstrating that every task has been completed:
| Name | Task | Verification |
|---|---|---|
| Anthony | 1. Events pulled down into app | 1.Demonstration of the functionality |
| 2. password reset functionality | 2. screenshot of email | |
| 3. display featured events | 3. Demonstration of functionality | |
| Darren | 1. Implement User Pages | 1. A demonstration of the website running locally |
| 2. Setting up GitHub actions on the new repo | 2. Screenshot of the settings on GitHub | |
| Sai | 1. Linking the Database to the Ticket Generation | 1. Screenshots of Codes of Ticket Generation |
| 2. Adding Logic to add Different Entities to the DB | 2. Screenshots of the Codes in VS Code | |
| Manikala | 1. Create a temp page for viewing/editing/deleting | 1. Screenshot of vs code |
| 2.Creating a temp page for creating elements. | 2. Screenshot of vs code | |
| 3.Path web pages with simple redirects. | 3. Screenshot of pages |