Planned Project Timeline & TODOs - ddrago/Bose-Frames-Audio-AR GitHub Wiki
Timeline to organize and keep in mind the progress necessary for the project.
Semester 1 Timeline:
W1 Monday 20 September 9:00: Projects bidding begin
W1 Wednesday 22 September 17:00: Projects bidding ends
- W3 Friday 8 October: literature review
- W4 Friday 15 October: sketching possible UI input and output methods
- W5 Friday 22 October: sketching possible hierarchical structures of the menu
- W6 Friday 29 October: figure out ray casting with head tracking with Frames
- W7 Friday 5 November: implement head-tracking-based menu/menu-item prototype(s)
- W8 Friday 12 November: implement dialogue-agent-based menu/menu-item prototype
- W9 Friday 19 November: implement head-tracking-based UI prototype
- W10 Friday 26 November: implement dialogue-agent-based UI prototype
- W11 Friday 3 December: implement dialogue-agent-based UI prototype
W12 Monday 6 December 9:00: Project crunch period begins
- W12 -
- W13 -
- W13 Tuesday 7 December 13:00 – 15:00: This session will cover planning for the remainder of the semester, writing your dissertation and evaluating your project.
W13 Friday 17 December 9:00: Project crunch period ends
TODOs:
Lit Review:
- read the papers given by Steve.
General product:
- test resonance SDK.
- test the 5.1Mix that the frames supposedly allow
For Head-tracking UI (HTI):
- [DONE] make selectable menu items based on pseudo-cursor position.
- test/develop orientation-recalibration of the frames
- If that works try setting up an app/html page on the phone that uses the phone's directional data to recalibrate the frames
- If that ^ does not work try gesture-activated recalibration of the frames
For Conversational User Interface (CI):
- get rasa X to work. If that fails ask Steve for funding for Google's assistant or Alexa.
For Gesture-based UI (GBI):
- make a novel gesture and test reliability.