Week 1: (13-19 February)
Task | Type | Estimated Time | Time Taken |
---|---|---|---|
Created communication plan Issue : #1, created a page for it here | Documentation | 20 min | 20 min |
Created Meeting Notes Template Issue : #6 created page for it here | Documentation | 45 min | 50 min |
Created a wiki-page for personal page templateIssue : #9 page is here | Documentation | 25 min | 20 min |
Filled branch section of Git Research Issuse : #21 page is here | Research & Documentation | 55 min | 60 min |
Week 2: (20-27 February)
Task | Type | Estimated Time | Time Taken |
---|---|---|---|
Added favorite repo to wiki #Issue : #26 page is here | Research & Documentation | 45 min | 30 min |
Created personal wikipage #Issue : #34 page is here | Documentation | 25 min | 20 min |
Week 3: (28 February-5 March)
Task | Type | Estimated Time | Time Taken |
---|---|---|---|
I had "Issue Guidlines" documentation task Issue : #43, created a page for it here | Research & Documentation | 2hr min | 1hr 30 min |
I had "Wikidata API and Wikidata Query Service Guidlines" documentation task Issue : #46, created a page for it here | Research & Documentation | 2hr min | 1hr 30 min |
Week 4: (6-12 March)
Task | Type | Estimated Time | Time Taken |
---|---|---|---|
Sidebar was redesigned and rearranged | Documentation | 1 hr | 55 min |
Working on Figma tool to use in Milestone-1 Mockups | Research | 1 day | 2 day |
Week 5: (13-19 March)
Task | Type | Estimated Time | Time Taken |
---|---|---|---|
Started and worked on Scenarious for Milestone-1 #50 , created a page for it here | Design & Implementation | 3 days | 2.5 days |
Started and worked on Mockups for Milestone-1 #55 , created a page for it here | Design & Implementation | 3 days | 2.5 days |
Reviewed Requirements and Scenarios with team | Review | 2 hrs | 3 hr |
Attented Customer Meeting | Meeting | 1 hr | 55 min |