Progress Summary
Our objective for the following week will be to review our project by reverifying the project requirements and the UML diagrams while on-boarding our welcomed teammates. Additionaly, we will be preparing the project plan and the responsibility assignment matrix (RAM). Also we are going to make research about the possible technologies that we can use throughout the development process.
Our plans for the next week
Description | Issue | Assignee | Due | Estimated Duration |
---|---|---|---|---|
Reverify the project requirements | #240 | Team | 10.10.2023 | 1hr |
Reverify the UML diagrams if needed | -- | Bengisu, Zülal, Leyla | 10.10.2023 | 1hr |
Update wiki pages if needed | -- | Leyla | 10.10.2023 | 1hr |
Decide on what technologies are going to be used for the front-end | #249 | Front-end team | 10.10.2023 | 1.5hr |
Decide on what technologies are going to be used for the back-end | #248 | Back-end team | 10.10.2023 | 1.5hr |
Prepare the project plan | #243 | Team | 10.10.2023 | 3.5hr |
Prepare the Responsibility Assignment Matrix (RAM) | #246 | Hakan, Mehmet, Arda, Abdullah | 10.10.2023 | 2hr |
Adding Personal Wiki Pages | #245, #237 | Bengisu, Ömer Faruk | 10.10.2023 | 1hr |
Risks
During our meeting, we talked about different frameworks that we can use. If we decide to use Flutter, we may encounter some performance issues. In addition, our team is not highly experienced in other frameworks that we listed in the meeting. If we choose one of them, We may need to spend a lot of time learning the fundamentals of these tools.
Participants
- Ahmed Bera Pay
- Ahmet Abdullah Susuz
- Ali Mert Geben
- Arda Arslan
- Bengisu Kübra Takkin
- Hakan Emre Aktaş
- Leyla Yayladere
- Mehmet Süzer
- Ömer Faruk Ünal
- Ömer Şükrü Uyduran
- Zülal Molla