Project Development Weekly Progress Report
Team Name: Rapid Response (Disaster Response Platform)
Date: 03.10.2023
Progress Summary
This week focused on updating the design documents and deciding on the general structure of the project. We set up the initial codebase for the back-end, the front-end, and the mobile. We decided on the technologies that will be used. We made several updates to the class diagram and the use case diagram. Our objective for the following week will be to connect the back-end with the front-end and the mobile.
What was planned for the week? How did it go?
Description |
Issue |
Assignee |
Due |
PR |
Estimated Duration |
Actual Duration |
Re-verify the requirements |
#1 |
Team |
27.09.2023 |
#21 |
1hr |
1.5hr |
Update the class diagram w.r.t. the changes in the requirements |
#2 |
Team |
29.09.2023 |
#22 |
4hr |
5hr |
Update the use case diagram w.r.t. the changes in the requirements |
#3 |
Team |
29.09.2023 |
#23 |
4hr |
7hr |
Update the sequence diagram w.r.t. the changes in the requirements |
#4 |
Team |
29.09.2023 |
-- |
4hr |
5hr |
Decide on what technologies are going to be used for the front-end |
#5 |
Front-Team |
02.10.2023 |
-- |
1hr |
30mins |
Decide on what technologies are going to be used for the back-end |
#6 |
Back-Team |
02.10.2023 |
#26 |
1hr |
30mins |
Decide on what technologies are going to be used for the mobile |
#7 |
Mobile-Team |
02.10.2023 |
#27 |
1hr |
45mins |
Cross-team technology sync - verify that these technologies are compatible |
#8 |
Team |
02.10.2023 |
#28 |
1hr |
15mins |
Completed tasks that were not planned for the week
Description |
Issue |
Assignee |
Due |
PR |
Set up the initial codebase for the back-end |
#9 |
Alice |
05.10.2023 |
#29 |
Planned vs. Actual
- We planned to decide on the front-end technologies by this week (#5). Even though we made a very fruitful discussion on the technologies that will be used for the front-end, we did not finalize the decision. Options are reduced to React and Vue. We will finalize the decision next week.
Your plans for the next week
Description |
Issue |
Assignee |
Due |
Estimated Duration |
Decide on what technologies are going to be used for the front-end |
#5 |
Front-Team |
02.10.2023 |
1hr |
Create resource, user, and action data models together with their CRUD operations |
#10 |
Ayse |
05.10.2023 |
2hr |
Create facilitator, responder, coordinator, and victim data models by extending the user data model |
#11 |
Ali |
07.10.2023 |
3.5hr |
Create an EC2 host machine and write a GitHub action that will sync the host machine when there is a push to the main/release branch |
#12 |
Alice |
07.10.2023 |
15mins |
Risks
- Extended user roles (e.g., facilitator, responder) may require additional fields that we did not consider in the initial design. We will address these issues as they arise.
...