Participated Meeting 4.1. Reviewed the project requirements, also scenarios and mockups.
1 hour
Meeting
Week 5 (29/03/2022 - 04/04/2022):
#
Task
Duration
Type of Work
1
Attended Customer Meeting 2. Got feedback about requirements and discussed with the team.
2 hours
Meeting
2
Participated Meeting 5.1 and discussed about chatbot requirements. Reviewed customer meeting notes.
2 hours 30 minutes
Meeting
3
Looked over the old repositories for use case, class and sequence diagram.
1 hour
Research
4
Participated Meeting 5.2. Created Use Case Diagram with the team. I focused on creating post and articles hierarchy.
2 hours
Meeting, Documentation
5
Participated Meeting 5.3. Reviewed Use Case Diagram and started Class Diagram with the team. I focused on Comment and Post classes. Decided sequence diagrams and distribute among the team members.
4 hours
Meeting, Documentation
6
Added weekly effort table.
45 minutes
Documentation
Week 6 (05/04/2022 - 11/04/2022):
#
Task
Duration
Type of Work
1
Attended Meeting 6.1. Worked on RAM and reviewed our Sequence Diagrams with the whole team.
2 hours
Meeting, Discussion, Documentation
2
Attended Meeting 6.2 and started to create Project Plan. Reviewed customer meeting notes.
2 hours 30 minutes
Meeting, Discussion, Documentation
3
Created issue #58 about Sequence Diagram of reporting a comment
10 minutes
Documentation
4
Worked on Sequence Diagram of reporting a comment with some of my group members.
1 hours 30 minutes
Meeting, Documentation
5
Attended Customer Meeting 3. Discussed with TA about the Use Case and Sequence Diagrams.
2 hours
Meeting
6
Helped the process of creating "Editing post, adding location" Sequence Diagram as described in the issue #59.
1 hour
Meeting, Documentation
7
Helped the process of creating "Creating a discussion thread" Sequence Diagram as described in the issue #55.
Attended Customer Meeting 4. Got feedbacks about Project Plan and Sequence Diagrams.
2 hours
Meeting
2
Attended Meeting 7.1. Worked on Project Plan, Milestone 1 with the whole team.
3 hours
Meeting, Discussion, Documentation
3
Created a title page with Kerem as the issue #68 says.
1 hour
Meeting, Documentation
4
Wrote my part of Individual Works part of the Milestone 1 Report.
1 hour 30 minutes
Documentation
5
Added weekly effort table.
30 minutes
Documentation
Week 8 (19/04/2022 - 25/04/2022):
#
Task
Duration
Type of Work
1
I'm looking into REST APIs, HTTP, and the overall framework of web applications.
2 hours
Research
2
Reading documentation and conducting research on the Flask and Django frameworks.
2 hours
Research
3
Added weekly effort table.
10 minutes
Documentation
Week 10 (03/05/2022 - 09/05/2022):
#
Task
Duration
Type of Work
1
Attending Meeting 10.1, where we discussed Practice Application..
2 hours
Meeting
2
Attending Meeting 10.2, where we decided on the framework of the practice app and divided work between us.
2 hours
Meeting, Discussion, Documentation
3
Added weekly effort table.
15 minutes
Documentation
Week 11 (17/05/2022 - 23/05/2022):
#
Task
Duration
Type of Work
1
Opening issue #96 regarding the implementation of the practice application's rate-post endpoint.
15 minutes
Documentation
2
Implementing rate-post endpoint and opened pull request #126
10 hours
Implementation
3
I realized a bug about the implementation and fixed this bug. Opened pull request #128
1 hour
Implementation
4
Added weekly effort table.
30 minutes
Documentation
Week 12 (10/05/2022 - 16/05/2022):
#
Task
Duration
Type of Work
1
Attended Meeting 12.1. During the meeting, we produced the class diagram, use case diagram, and project plan. I worked on these with the rest of my group.
3 hours
Meeting, Documentation
2
Attended Meeting 12.2. With the help of my group members, we've launched our practice app.
2 hours
Meeting, Implementation
3
I wrote my part in the Milestone Report 2.
1 hour
Documentation
4
Attended Meeting 12.3. We have completed our milestone report and have published it to the Moodle website as a group.