Week #1 (22.03.2021 - 29.03.2021)
-
- Task: Team meeting.
- Date and Time: 26 March 2021, 21:30 - 22:10
- Duration: 40 mins
- Type of Work: Discussion and job splitting
-
- Task: Preperation of communication plan and adding it to wiki.(Issue #2)
- Date and Time: 27 March 2021, 23:00- 23:30
- Duration: 30 mins
- Type of Work: Wiki page preperation
-
- Task: Created personal wiki page.
- Date and Time: 27 March 2021, 23:30 - 23:59
- Duration: 30 mins
- Type of Work: Wiki page preperation
-
- Task: Repository research.
- Date and Time: 28 March 2021, 20:00- 20:45
- Duration: 45 mins
- Type of Work: Research
-
- Task: watched git for ages 4 and up video.
- Date and Time: 28 March 2021, 17:30 - 19:00
- Duration: 90 mins
- Type of Work: Self improvement
-
- Task: git research
- *Date and Time: 28 March 2021, 19:00 - 20:00
- Duration: 60 mins
- Type of Work: Research
-
- Task: Creating this page.
- Date and Time: 28 March 2021, 20:45 - 21:15
- Duration: 30 mins
- Type of Work: Wiki page preperation
-
Total: 5,5 hours
Week #2 (30.03.2021 - 05.04.2021)
-
- Task: Reading about project options
- Date and Time: 30 March 2021, 14:30 - 15:00
- Duration: 30 mins
- Type of Work: Reading & Analyzing
-
- Task: Project Selection Meeting.
- Date and Time: 30 March 2021, 22:30 - 23:15
- Duration: 45 mins
- Type of Work: Group discussion
-
- Task: Research about similar projects
- Date and Time: 03 April 2021, 15:00- 16:00
- Duration: 60 mins
- Type of Work: Research
-
- Task: Meeting in a subgroup to talk about System Requirements (w/Batuhan Tongarlak & Ömer Yılmaz)
- Date and Time: 03 April 2021, 21:30- 23:00
- Duration: 90 mins
- Type of Work: Meeting, discussion and preparing a report for the other group members
-
- Task: Team Meeting for Arranging the Requirements Page
- *Date and Time: 5 April 2021, 20.30 - 22.00
- Duration: 90 mins
- Type of Work: Meeting and discussion, Requirements elicitation
-
- Task: Reviewing the System Requirements Page
- *Date and Time: 5 April 2021, 23.30 - 24.00
- Duration: 30 mins
- Type of Work: Wiki page
-
- Task: Creating Related Softwares Tables page
- *Date and Time: 6 April 2021, 01.00 - 2.00
- Duration: 60 mins
- Type of Work: Wiki page
-
Total: ~6 hours 45 minutes
Week #3 (05.04 - 12.04)
-
- Task: Reviewing requirement questions
- Duration: 60 mins
- Type of Work: Analysis
- Total: ~1 hour
Week #3 (12.04 - 19.04)
-
- Task: Customer meeting
- Date and Time: 15 April 2021, 17.00-18.45
- Duration: 105 mins
- Type of Work: Meeting
- Customer Meeting #1
-
- Task: Meeting with Group about customer meeting
- Date and Time: 15 April 2021, 21.00-22.00
- Duration: 60 mins
- Type of Work: Meeting
- Meeting #5
-
- Task: Meeting with Group about Mockups
- Date and Time: 17 April 2021, 21.00-23.30
- Duration: 150 mins
- Type of Work: Meeting
- Meeting #6
-
- Task: Creating Scenario #3 and designing web pages
- Date and Time: 18 April 2021, 15.00-20.00
- Duration: 300 mins
- Type of Work: Design
-
- Task: Creating Scenario #3 wiki pages
- Date and Time: 19 April 2021, 19.00-20.30
- Duration: 90 mins
- Type of Work: Wiki Page
- Scenario #3.1
- Scenario #3.2
-
- Task: Review other Scenarios
- Date and Time: 19 April 2021, 18.00-19.00
- Duration: 60 mins
- Type of Work: Review
-
- Task: Updating personal efforts page
- Date and Time: 19 April 2021, 20.30-21.00
- Duration: 30 mins
- Type of Work: Personal Efforts
-
Total: ~13 hours 15 minutes
Week #5 (20.04.2021 - 26.04.2021)
-
- Task: Attended meeting with Suzan Hoca.
- Date and Time: 20.04.2021, 22:00 - 23:15
- Duration: 75 mins
- Type of Work: Meeting - discussion
-
- Task: Attended [meeting #7][Meeting7]
- Date and Time: 21.04.2021, 21:00 - 21:30
- Duration: 30 mins
- Type of Work: meeting - job splitting
-
- Task: Revised requirements in the light of meeting with Suzan Hoca. issue
- Date and Time: 22.04.2021, 20:00 - 21:00
- Duration: 60 mins
- Type of Work: Documentation - wiki - requirements
-
- Task: Working on use case diagram. Issue
- Date and Time: 22.04.2021, 18:00 - 20:00
- Duration: 2 hours
- Type of Work: Use case diagram
-
- Task: Attended [Customer Meeting #2][Customer2] with Suzan Hoca and Serdar Hoca.
- Date and Time: 24.04.2021, 17.00 - 18:00
- Duration: 60 mins
- Type of Work: Meeting - requirements
-
- Task: Attended [Meeting #8][Meeting8].
- Date and Time: 25.04.2021, 20:30 - 21:30
- Duration: 60 mins
- Type of Work: meeting - job splitting - design issues
-
- Task: Revised use case diagram in the light of new requirements. Issue
- Date and Time: 26.04.2021, 22:00 - 23:00
- Duration: 60 mins
- Type of Work: use case diagram - documentation
-
- Task: Editing Personal efforts.
- Date and Time: 26.04.2021, 23:00- 23:15
- Duration: 15 mins
- Type of Work: Wiki - Documentation
-
Total: 8 hours
Week #6 (26.04 - 03.05)
-
- Task: Sequence diagram #3, 'Getting token for a group goal', prepared on Draw.io
- Duration: 1.5 hour
- Type of Work: Task
-
- Task: Reviewing Class-Diagrams, other Sequence-Diagrams
- Duration: 30 mins
- Type of Work: Organization
-
- Task: Personal table of work
- Duration: 15 mins
- Type of Work: Task
-
- Task: Attend meeting #9, milestone report task sharing
- Duration: 1 hour
- Type of Work: Meeting
-
- Task: Arranging tasks for Cmpe451 for RAM with Gökay
- Duration: 2 hours
- Type of Work: Task, Documentation
-
- Task: Attended Meeting #10
- Duration: 1 hour
- Type of Work: Meeting
-
Total time: 6 hours
Week #7 (26.04 - 03.05)
-
- Task: Assigning RAM tasks with Gökay
- Duration: 60 mins
- Type of Work: Task, Documentation
Total time: 1 hour
Week #5 (09.11.2021 - 16.11.2021)
- Task: Attending group meeting at lab session.
- Date and Time: 09.11.2021
- Duration: 2 hours
- Type of Work: Meeting
- Task: Implementing Goal Pages for Frontend issue #259, pr #269
- Date and Time: 12.11.2021 - 14.11.2021
- Duration: 16 hours
- Type of Work: Coding
- Task: Meeting with Frontend team, organizing structure.
- Date and Time: 13.11.2021
- Duration: 3 hours
- Type of Work: Meeting
- Task: Helping Batuhan for Creating entity pages issue
- Date and Time: 15.11.2021
- Duration: 4 hour
- Type of Work: Coding, Review
- Task: Worked on scenario with the team.
- Date and Time: 16.11.2021
- Duration: 1 hour
- Type of Work: Presentation
Total: 29 hours
Week #6 (16.11.2021 - 23.11.2021)
- Task: Attending customer presentation, presenting and listening other presentations.
- Date and Time: 16.11.2021, 13:00 - 17:00
- Duration: 4 hours
- Type of Work: Presentation
- Task: Writing individual milestone report.
- Date and Time: 19.11.2021
- Duration: 2 hours
- Type of Work: Milestone report
- Task: Written Frontend part of the "evaluation of tools and processes we used to manage project" of milestone report.
- Date and Time: 20.11.2021
- Duration: 60 mins
- Type of Work: Milestone report, Documentation
Total: 7 hours
Week #7 (23.11.2021 - 30.11.2021)
- Task: Attending group meeting at lab session.
- Date and Time: 23.11.2021, 15:00 - 17:00
- Duration: 2 hours
- Type of Work: Meeting
Total: 2 hours
Week #8 (30.11.2021 - 07.12.2021)
- Task: Attending group meeting at lab session.
- Date and Time: 30.11.2021, 15:00 - 17:00
- Duration: 2 hours
- Type of Work: Meeting
- Task: Define Tasks for next week, create issues, distribute them among team members. issue #329,issue #330,issue #331,issue #332
- Date and Time: 5.12.2021
- Duration: 2 hours
- Type of Work: Team Management
- Task: Work On issue #329
- Date and Time: 06.11.2021
- Duration: 4 hours
- Type of Work: Coding
Total: 8 hours
Week #9 (07.12.2021 - 14.12.2021)
- Task: Attending group meeting 8 at lab session.
- Date and Time: 07.12.2021, 15:00 - 17:00
- Duration: 2 hours
- Type of Work: Meeting
- Task: Work On the issue and finalize it. issue #329, pr #390
- Date and Time: 12.12.2021
- Duration: 6 hours
- Type of Work: Coding
- Task: Work On the issue and finalize it. issue #332, pr #390
- Date and Time: 13.12.2021
- Duration: 6 hours
- Type of Work: Coding
- Task: Work On the presentation
- Date and Time: 14.12.2021
- Duration: 2 hour
- Type of Work: Presentation
Total: 16 hours
Week #10 (14.12.2021 - 21.12.2021)
- Task: Attending group meeting at lab session.
- Duration: 2 hours
- Type of Work: Meeting
- Task: Meeting with Batuhan to clear the entity-goal structure
- Duration: 1 hours
- Type of Work: Meeting
Total: 3 hours
Week #11 (21.12.2021 - 28.12.2021)
- Task: Attending the lab hour group meeting
- Duration: 2 hours
- Type of Work: Meeting
- Task: Frontend group meeting to generally investigate what we will do and arrange our work
- Duration: 1 hour
- Type of Work: Meeting
Total: 3 hours
Week #12 (28.12.2021 - 04.01.2022)
- Task: Attending the lab hour group meeting
- Duration: 2 hours
- Type of Work: Meeting
- Task: Create Profile page for users
- Issues and Pull Requests: https://github.com/bounswe/2021SpringGroup12/issues/444 https://github.com/bounswe/2021SpringGroup12/pull/530
- Duration: 4 hour
- Type of Work: Code, Implementation
- Task: Creating unittests for goal, group goal pages
- Issues and Pull Requests: https://github.com/bounswe/2021SpringGroup12/issues/446 https://github.com/bounswe/2021SpringGroup12/issues/527 https://github.com/bounswe/2021SpringGroup12/pull/539
- Duration: 2 hour
- Type of Work: Code, Implementation
- Task: Displaying group goals has a problem
- Issues and Pull Requests: https://github.com/bounswe/2021SpringGroup12/issues/518 https://github.com/bounswe/2021SpringGroup12/pull/532
- Duration: 2 hour
- Type of Work: Coding, Bugfix
- Task: Create publish, republish, unpublish buttons for the goal
- Issues and Pull Requests: https://github.com/bounswe/2021SpringGroup12/issues/533 https://github.com/bounswe/2021SpringGroup12/pull/536
- Duration: 2 hour
- Type of Work: Coding, Implementation
- Task: Edit Goal page is not loading
- Issues and Pull Requests: https://github.com/bounswe/2021SpringGroup12/issues/537 https://github.com/bounswe/2021SpringGroup12/pull/538
- Duration: 1 hour
- Type of Work: Code, Implementation
- Task: Prototype pages for Goal, subgoal and entities.
- Issues and Pull Requests: https://github.com/bounswe/2021SpringGroup12/issues/540 https://github.com/bounswe/2021SpringGroup12/pull/544
- Duration: 4 hour
- Type of Work: Code, Implementation
- Task: Meeting for Final Milestone presentation
- Duration: 2 hour
- Type of Work: Meeting
Total: 19 hours