1 |
August 19, 2019 - August 25, 2019 |
Project Idea and researches |
2 |
August 25, 2019 |
I talked with Assaf Spanier to choose the project and the moderator |
3 |
August 30, 2019 |
I talked with the moderator Eli Eissak about the project |
4 |
September 8, 2019 |
I have changed the moderator to be Ihab Zahayka |
5 |
September 18, 2019 |
complete טופס התנעה |
6 |
October 1, 2019 |
Planning day,I start to plan what I have to do in the project |
7 |
November 4, 2019 |
Start writing טופס ההצעה |
8 |
November 9, 2019 |
Updating טופס ההצעה |
9 |
November 15, 2019 |
change in the work (from image processing to AutoCAD processing for plug-in) |
10 |
November 17, 2019 |
start studying for AutoCAD environment |
11 |
November 19, 2019 |
start studying about .NET framework |
12 |
November 25, 2019 |
studying about AutoCAD selection tool |
13 |
November 30, 2019 |
first AutoCAD plugin completed with selection and some of the expected results |
14 |
December 5, 2019 |
Updating טופס ההצעה |
15 |
December 8, 2019 |
Submitted טופס ההצעה |
16 |
December 17, 2019 |
Continue studying c# language |
17 |
December 25, 2019 - January 10, 2020 |
נלחצתי בעבודה שלי ולא יכלתי להתקדם בפרויקט |
18 |
January 11, 2020 |
Back to project with the selection tool and ability to count the selected objects |
19 |
January 14, 2020 |
working on the objects and I can reach the coordinates for each line |
20 |
January 17, 2020 |
working on the analyzing of the lines and arrows detecting |
21 |
January 19, 2020 |
I found the direction for each arrow |
22 |
January 22, 2020 |
Start working on דוח אלפה |
22 |
January 24, 2020 |
Updating דוח אלפה |
23 |
January 25, 2020 |
Submitted דוח אלפה |
24 |
February 5, 2020 |
changing of the analyzing algorithm to be more public |
25 |
February 15, 2020 |
all the arrows are able to analyze and determine |
26 |
February 22, 2020 |
I found the angles direction for each arrow |
27 |
February 27, 2020 |
editing the analyzing algorithm to be more accurate |
28 |
March 3, 2020 |
the pedestration lines has been analyzed |
29 |
March 10, 2020 |
Now i know how to edit on autocad and changing the colors, the pedestration lines becomes yellew and the arrows becomes red |
30 |
March 17, 2020 |
I found the turn angle for each arrow |
31 |
March 22, 2020 |
we watched the online lecture with dr. Assaph |
32 |
March 23, 2020 |
Start working on analyzing routs |
33 |
March 30, 2020 |
Finding the pairs of arrows that forms the enterance and the exit of the crossroad for each route |
34 |
April 7, 2020 |
Start working on the work schedule report |
35 |
April 15, 2020 |
Submitted work schedule report |
36 |
April 18, 2020 |
Continue finding the pairs of arrows |
37 |
April 25, 2020 |
All the pairs of arrows has been detected |
38 |
April 30, 2020 |
Now I can draw new lines to Autocad |
39 |
May 2, 2020 |
all the routes has been drawed as straight line by the pairs arrows |
40 |
May 5, 2020 |
fix the left turn routes to be accurate and real (curved lines, not straight) |
41 |
May 10, 2020 |
working on contraints algorithm to find the cases of traffic lights and use the intersection of drawn routes |
42 |
May 13, 2020 |
Start working on דוח בטא |
43 |
May 15, 2020 |
Submitted דוח בטא |
44 |
May 23, 2020 |
All the intergreen cases can be found for each route |
45 |
May 30, 2020 |
the optimal traffic schedule can be found and calculated |
46 |
June 7, 2020 |
start working on the format of the imported and exported file |
47 |
June 10, 2020 |
The analyzed data can be expoted as XML file |
48 |
June 12, 2020 |
start working on the second Command in order to calculate by importing XML File |
49 |
June 18, 2020 |
Done after using regex in the analyzing text |
50 |
June 23, 2020 |
the pedestrian routes can be found |
51 |
June 28, 2020 |
the pedestrian routes result inserted into the calculation |
52 |
June 30, 2020 |
update the second command calculating algorythm after pedestrian modification |
53 |
July 1, 2020 |
start working on the last report |
54 |
July 7, 2020 |
updating the last report |
55 |
July 9, 2020 |
submitting the last report |