What did we do well?
- Presentation went well.
- Code reviews were done.
- We started doing bugs
- we did more unit test
- Good team coordination when preparing for the presentation.
what we didn't do so well on?
- Code reviews were done late
- Bugs increased
- a lot of changes were made to fix the bugs
- features weren't 100% complete by the time of presentation
Solutions
- Start the code review early
- solve the bugs as we go
- rather than last-minute changes, make the changes early.
future suggestion
- Everyone should have their part done no later than the Monday of the week of the presentation and submit a pull request
- Plan on using the Tuesday of the week of the presentation to finish any remaining pull requests and merge those features into master.