Project Plan - TalatCikikci/BounSwe573Repo GitHub Wiki

Table of Contents

Description

Below is the project plan for BuKoop Project. Plan consists of milestones, tasks and subtasks.

  • Level 1 tasks are indicated by bold font and has a ► symbol.
  • Milestones are the "tasks" that have a duration of "0 days". Deliverables of these milestones can be seen in the "Deliverables" column.
  • Subtasks of Level 2 tasks are indicated by pipes (╔ , ╠ , ╚ ) linking them.

Project Plan

Task Nr. Task Name Duration Start Finish Deliverables
1 ► Requirements Elicitation 21 days Tue 16.02.16 Mon 07.03.16
1.1 Create GitHub Repository 1 hr Tue 16.02.16 Tue 16.02.16
1.2 Research Related Topics 2 days Tue 16.02.16 Thu 18.02.16
1.3 Create Software Specifications Draft 5 days Thu 18.03.16 Tue 23.02.16
1.4 Review Software Specifications 2 hrs Tue 23.02.16 Tue 23.02.16
1.5 Gather Feedback on Software Specifications 2 hrs Tue 23.02.16 Tue 23.02.16
1.6 Rework Software Specifications 4 days Tue 23.02.16 Sat 27.02.16
1.7 Create Mockups of the System 3 days Sat 27.02.16 Tue 01.03.16
1.8 Software Requirements Validation 3 hrs Tue 01.03.16 Wed 01.03.16
1.9 Finalize Software Specifications 4 days Wed 02.03.16 Sun 05.03.16
1.10 Prepare Project Plan 2 days Sun 06.03.16 Mon 07.03.16
1.11 Requirements Elicitation Complete 0 days Mon 07.03.16 Mon 07.03.16 Requirements Specification Document; Project Plan
2 ► Design 9 days Tue 08.03.16 Wed 16.03.16
2.1 Analyze Finalized Software Specifications 1 day Tue 08.03.16 Tue 08.03.16
2.2 Research Applicable Design Patterns 1 day Wed 09.03.16 Wed 09.03.16
2.3 Draft Design Specifications Document 5 days Thu 10.03.16 Mon 14.03.16
2.4 Review Design Specifications Document 1 day Tue 15.03.16 Tue 15.03.16
2.5 Finalize Design Specifications Document 1 day Wed 16.03.16 Wed 16.03.16
2.6 Design Complete 0 days Wed 16.03.16 Wed 16.03.16 Design Specification Document
3 ► Development 49 days Thu 17.03.16 Wed 04.05.16
3.1 Sprint 1 5,75 days Thu 17.03.16 Tue 22.03.16
3.1.1 ╔ Sprint Plan 2 hrs Thu 17.03.16 Thu 17.03.16
3.1.2 ╠ Develop Planned Features 5 days Thu 17.03.16 Tue 22.03.16
3.1.3 ╠ Prepare Unit Tests 4 hrs Tue 22.03.16 Tue 22.03.16
3.1.4 ╠ Prepare Functional Tests 4 hrs Tue 22.03.16 Tue 22.03.16
3.1.5 ╚ Sprint 1 Complete 0 days Tue 22.03.16 Tue 22.03.16 Customer Demo Version 0.1
3.2 Sprint 2 6,75 days Tue 22.03.16 Tue 29.03.16
3.2.1 ╔ Sprint Plan 2 hrs Tue 22.03.16 Tue 22.03.16
3.2.2 ╠ Develop Planned Features 6 days Wed 23.03.16 Mon 28.03.16
3.2.3 ╠ Prepare Unit Tests 4 hrs Tue 29.03.16 Tue 29.03.16
3.2.4 ╠ Prepare Functional Tests 2 hrs Tue 29.03.16 Tue 29.03.16
3.2.5 ╚ Sprint 2 Complete 0 days Tue 29.03.16 Tue 29.03.16 Customer Demo Version 0.2
3.3 Sprint 3 7,75 days Tue 29.03.16 Tue 05.04.16
3.3.1 ╔ Sprint Plan 2 hrs Tue 29.03.16 Tue 29.03.16
3.3.2 ╠ Develop Planned Features 7 days Tue 29.03.16 Tue 05.04.16
3.3.3 ╠ Prepare Unit Tests 4 hrs Tue 05.04.16 Tue 05.04.16
3.3.4 ╠ Prepare Functional Tests 2 hrs Tue 05.04.16 Tue 05.04.16
3.3.5 ╚ Sprint 3 Complete 0 days Tue 05.04.16 Tue 05.04.16 Customer Demo Version 0.3
3.4 Sprint 4 6,75 days Tue 05.04.16 Tue 12.04.16
3.4.1 ╔ Sprint Plan 2 hrs Tue 05.04.16 Tue 05.04.16
3.4.2 ╠ Develop Planned Features 6 days Wed 06.04.16 Mon 11.04.16
3.4.3 ╠ Prepare Unit Tests 4 hrs Tue 12.04.16 Tue 12.04.16
3.4.4 ╠ Prepare Functional Tests 2 hrs Tue 12.04.16 Tue 12.04.16
3.4.5 ╚ Sprint 4 Complete 0 days Tue 12.04.16 Tue 12.04.16 Customer Demo Version 0.4
3.5 Sprint 5 7,75 days Tue 12.04.16 Tue 19.04.16
3.5.1 ╔ Sprint Plan 2 hrs Tue 12.04.16 Tue 12.04.16
3.5.2 ╠ Develop Planned Features 7 days Tue 12.04.16 Tue 19.04.16
3.5.3 ╠ Prepare Unit Tests 4 hrs Tue 19.04.16 Tue 19.04.16
3.5.4 ╠ Prepare Functional Tests 2 hrs Tue 19.04.16 Tue 19.04.16
3.5.5 ╚ Sprint 5 Complete 0 days Tue 19.04.16 Tue 19.04.16 Customer Demo Version 0.5
3.6 Sprint 6 6,75 days Tue 19.04.16 Tue 26.04.16
3.6.1 ╔ Sprint Plan 2 hrs Tue 19.04.16 Tue 19.04.16
3.6.2 ╠ Develop Planned Features 6 days Wed 20.04.16 Mon 25.04.16
3.6.3 ╠ Prepare Unit Tests 4 hrs Tue 26.04.16 Tue 26.04.16
3.6.4 ╠ Prepare Functional Tests 2 hrs Tue 26.04.16 Tue 26.04.16
3.6.5 ╚ Sprint 6 Complete 0 days Tue 26.04.16 Tue 26.04.16 Customer Demo Version 0.6
3.7 Sprint 7 7,75 days Tue 26.04.16 Tue 03.05.16
3.7.1 ╔ Sprint Plan 2 hrs Tue 26.04.16 Tue 26.04.16
3.7.2 ╠ Develop Planned Features 7 days Tue 26.04.16 Tue 03.05.16
3.7.3 ╠ Prepare Unit Tests 4 hrs Tue 03.05.16 Tue 03.05.16
3.7.4 ╠ Prepare Functional Tests 2 hrs Tue 03.05.16 Tue 03.05.16
3.7.5 ╚ Sprint 7 Complete 0 days Tue 03.05.16 Tue 03.05.16 Customer Demo Version 0.7
3.8 Development Complete 0 days Tue 03.05.16 Tue 03.05.16 Functional Test Cases
4 ► System Test 7 days Tue 03.05.16 Tue 10.05.16
4.1 Test Completed Product 2 days Tue 03.05.16 Thu 05.05.16
4.2 Bugfix 3 days Thu 05.05.16 Sun 08.05.16
4.3 Regression Test 1 day Sun 08.05.16 Mon 09.05.16
4.4 Review Documentation 1 day Mon 09.05.16 Tue 10.05.16
4.5 Product Release 0 days Tue 10.05.16 Tue 10.05.16 Release Version of the Product; Test Report