Last week activities:
- 26/08/24 weekly meeting, drafting of fifth weekly report
- 26/08/24 implementation of the pytesseract python library for OCR
- 27/08/24 implementation of the Character recognition with Pytesseract
- 29/08/24 finish the implementation of text recogniton
- 30/08/24 start with the image transcription implementation
Week Schedule:
- 02/09/24 weekly meeting, drafting of sixth weekly report
- 07/09/24 Preparation for deliverable 2 presentation
- 07/09/24 Publication of deliverable 2 on git hub's wiki
- 08/09/24 Final details and last push of the funtionalities of the project before secondo deliverable
To improve:
David Alejandro Ramírez
Last week activities:
- 26/08/24 weekly meeting, drafting of fourth weekly report
- 27/08/24 almost end with the text recognition library implementation
- 29/08/24 finish the implementation of text recogniton
- 30/08/24 start with the image transcription implementation
Week Schedule:
- 02/09/24 weekly meeting, drafting of sixth weekly report
- 07/09/24 Preparation for deliverable 2 presentation
- 07/09/24 Publication of deliverable 2 on git hub's wiki
- 08/09/24 Final details and last push of the funtionalities of the project before secondo deliverable
To improve:
- Team meetings for feedback and organization
Ana Sofia Alfonso Moncada
Last week activities:
- 26/08/24 weekly meeting, drafting of fifth weekly report
- 26/08/24 finish main functionality of text translation implementation
- 27/08/24 sprint labels update onto github's backlog
- 28/08/24 update home and register
- 29/08/24 start the change languages functionality for text translation implementation
Week Schedule
- 02/09/24 weekly meeting, drafting of sixth weekly report
- 03/09/24 continue with the change languages functionality for text translation implementation
- 04/09/24 Locate change languages button on home interface
- 05/09/24 First diagram for deliverable 2 creation
- 06/09/24 Second diagram for deliverable 2 creation
- 07/09/24 Preparation for deliverable 2 presentation
- 07/09/24 Publication of deliverable 2 on git hub's wiki
- 08/09/24 Final details and last push of the funtionalities of the project before secondo deliverable
To improve
- Working hours
- Team meetings for feedback and organization