Is the likelihood of this risk accurately assessed
Is this risk more likely to happen than predicted
Is this risk less likely to happen than predicted
Is the severity of this risk accurately assessed
If this risk were to happen would it be more severe than predicted
If this risk were to happen would it be less severe than predicted
Risk Plan
Are there any risks that have a higher risk factor that aren't on the risk plan
Can the risk be rearranged based on the new risk factor estimates?
Notes
Team Risk 7 is a duplicate Group members may be unable to contribute as much due to the Midterm season and the Thanksgiving holiday
We should have more
Team Risk 2 Miscommunication between team members
We think that the probability should be reduced to medium as we have better and more established communication within the team so its harder for huge miscommunication happen
Development Technologies Risk 1
We implemented most of what we wanted to with keycloak, there's still a couple unknowns so we're going to reduce the probability to medium
Testing Risk 1
Add investments in testability to the solution
Increase probability of this happening as we underestimated it in our testability in the first ID
Testing Risk 5
The risk isn't really a risk, but rather a problem that we don't have a consistent way of setting up testing and development environment
We do need to create a consistent method of setting up development and testing environment
Other Risk 1
We we talked to the stakeholder about our requirements, they agreed with all the ones that we had come up with, so it seems less likely that we'll misunderstand on a major point