1 ‐ OCI to Azure Migration Steps - SanjeevOCI/Azure GitHub Wiki
OCI to Azure Migration Steps:
1. Cost Estimation
Utilize the Azure Pricing Calculator to estimate migration costs from OCI to Azure. Adjust estimates based on your organization’s specific configurations and requirements.
2. Activities & Assignments
📌 Tasks and responsibilities assigned to respective teams.
Step | Activity | Responsible Team |
---|---|---|
1.1 | Cost Estimation using Azure Pricing Calculator | Architect |
2.1 | Document OCI Inventory | Architect |
2.2 | Plan Network Architecture in Azure | Architect |
2.3 | Obtain Sign-Off on Network Plan | Architect, Stakeholders |
2.4 | Implement Landing Zone in Azure | Architect |
2.5 | Provision App & Database Services | Architect |
2.6 | Establish OCI-Azure Connectivity | Architect |
2.7 | Request Data Sharing for Migration | App/DB Admin |
2.8 | Execute Data Transfer from OCI to Azure | Architect |
2.9 | Configure Application & Database in Azure | App/DB Admin |
2.10 | Validate Subnet Interconnectivity | Architect |
2.11 | Perform Application & Database Testing | Testing Team |
2.12 | Set Up Development Environment | Dev Team |
2.13 | Configure Test/UAT Environment | Testing Team |
2.14 | Deploy Production Environment | Prod/Testing Team |
2.15 | Execute Final Cutover to Azure | All Teams |
2.16 | Conduct Go/No-Go Review | All Teams, Client |
2.17 | Confirm Migration Completion & Post-Migration Review | All Teams |
3. Migration Process - Step by Step
3.1 Inventory Documentation (Architect)
- List all resources in OCI, including compute, storage, databases, networking, and other services.
- Identify dependencies and interconnections.
- Prepare a detailed inventory document with configurations.
3.2 Network Architecture Design (Architect)
- Design the network structure in Azure, defining VNets, subnets, NSGs, and other components.
- Ensure high availability and disaster recovery needs are addressed.
- Create a network diagram for approval.
3.3 Stakeholder Sign-Off (Architect)
- Review the network and migration plan with stakeholders.
- Implement feedback-based adjustments.
- Obtain formal approval before proceeding.
3.4 Landing Zone Implementation (Architect)
- Set up the initial Azure environment with resource groups, IAM roles, and policies.
- Establish foundational components like VNets, subnets, and management groups.
3.5 Application & Database Services Setup (Architect)
- Provision required compute resources (VMs, App Services, etc.) and databases (Azure SQL, Cosmos DB, etc.).
- Configure services to ensure compatibility and performance.
3.6 Secure OCI-Azure Interconnection (Architect)
- Establish secure connectivity between OCI and Azure using VPN, ExpressRoute, or other methods.
- Verify network communication and configurations.
3.7 Data Sharing Request (App/DB Admin)
- Coordinate with the application/database team to share necessary data for migration.
- Ensure all required datasets are identified and ready for transfer.
3.8 Data Migration Execution (Architect)
- Plan and execute data transfer from OCI to Azure using Azure Data Migration Service or other tools.
- Validate data integrity post-transfer.
3.9 Application/Database Setup (App/DB Admin)
- Set up applications and database servers in Azure.
- Perform necessary configurations and adjustments.
3.10 Subnet Connectivity Verification (Architect)
- Ensure proper interconnectivity between subnets within Azure.
- Validate routing, security, and performance settings.
3.11 Application & Database Testing (Testing Team)
- Conduct functional, performance, and security testing of migrated applications and databases.
3.12 Development Environment Setup (Dev Team)
- Set up and validate the development environment in Azure.
- Ensure all required tools and resources are available.
3.13 Test/UAT Environment Setup (Testing Team)
- Configure and validate the test/UAT environment in Azure.
- Conduct User Acceptance Testing (UAT) and resolve issues.
3.14 Production Environment Setup (Prod/Testing Team)
- Deploy and validate the production environment in Azure.
- Ensure operational readiness for final migration.
3.15 Final Cutover Execution (All Teams)
- Perform the final migration cutover to Azure.
- Monitor the process and address any issues promptly.
3.16 Go/No-Go Decision (All Teams & Client)
- Assess migration status and make the Go/No-Go decision.
- Ensure all critical concerns are resolved before going live.
3.17 Migration Completion & Post-Migration Review (All Teams)
- Confirm successful transition to Azure.
- Conduct a final review and provide post-migration support.