Sprint Two Retrospective - SIU-CS/DataDam-production GitHub Wiki

What went well

Each member completed most of their part of the code.

We committed more frequently.

We were better prepared for the presentation.

What could have been better

Integrating our code at more frequent intervals.

Started earlier on the code.

Trying to fix our github errors.

Actions for the next sprint

Start earlier on the code.

Integrate at more frequent rate.

Meet more frequently for coding nights.

Fix github issues to avoid future problems.

Create backup files in case of accidentally overwriting a branch.

Actions we did accomplish from first retrospective

Met on a more frequent basis to work on code as a team.

Better communication on the issues and code during the sprint.

Actions we didn't do from first retrospective.

We didn't start early on the code as we wanted to do after sprint one.

We didn't try to fix errors and issues with github due to time constraints.