Total hours: 59.1 hours

Day TimeStart End Comment Total Time spent:
1/19 5:20 PM 6:40 PM Reviewed the current website 1.3 hours
1/20 5:30 PM 7:30 PM Prospectus and reviewed the proposal, also client meeting 2 hours
1/26 5:00 PM 6:30 PM Looked at some Wordpress themes, also client meeting 1.5 hours
2/2 5:15 PM 7:15 PM Mock-ups of home page and application pagee 2 hours
2/3 2:00 PM 5:15 PM Design doc slideshow and then group session 3.25 hours
2/8 5:00 PM 9:00 PM Development environment set up, set up Wordpress Admin, read some documentation 4 hours
2/10 4:30 PM 5:30 PM Group meeting, Cloud9 workspace organized and then pushed to GitHub repo 1 hour
2/11 5:15 PM 6:30 PM Organized meeting times, asked Tony about what wordpress theme he wants 1.25 hours
2/15 4:00 PM 5:00 PM Drew up schema for dB 1 hour
2/18 5:15 PM 7:00 PM Met with Jason, planned for next week 1.75 hours
2/22 5:00 PM 6:30 PM Set up the new Cloud9 workspace as master branch in GitHub 1.5 hours
2/24 5:00 PM 7:00 PM Outlined goals for Milestone 1 2 hours
2/26 12:30 PM 3:30 PM Worked on Website with group using Cloud9 3 hours
2/27 1:30 PM 4:00 PM Worked on Website with group using Cloud9 3.5 hours
2/28 2:00 PM 5:30 PM Milestone prep and presentation 3.5 hours
3/3 5:30 PM 7:00 PM Weekly meeting with Client 1.5 hours
3/16 4:00 PM 6:00 PM Worked on website, discussed plans for Milestone 2 2 hours
3/17 4:30 PM 6:30 PM Met with Jason and had a meeting with client, prepared for weekend 2 hours
3/19 1:15 PM 5:15 PM Applied new theme to my branch, read through some documentation and created a new homepage 4 hours
3/21 8:30 PM 9:50 PM Set the new homepage to the one I made 1.3 hours
3/28 5:00 PM 6:00 PM Created the database for our applicants 1 hour
4/1 5:00 PM 6:00 PM Worked on database 1 hour
4/2 7:30 PM 9:30 PM Working on foreign keys for database 2 hours
4/3 5:15 PM 9:00 PM Completed database, updated homepage, and added speaking tour page 3.75 hours
4/4 7:00 PM 8:00 PM Created blog entries for speaking tour and looked into blogs for programs 1 hour
4/5 6:00 PM 9:00 PM Created blogs for all programs and organized them, also moved dB tables to C9 3 hours
4/6 2:00 PM 5:00 PM Usability session/design critique 3 hours
4/7 5:00 PM 6:00 PM Went over design notes gathered from usability inspection, went over notes and planned out changes to be implemented over the weekend 1 hour
4/9 2:00 PM