Day TimeStart End Comment Total Time : 52.4 Hours
2-10 4:30 5:30 Team meeting 1+
2-10 11:00pm 12:00 Worked on connecting github to Cloud 9 IDE 2+
2-11 4:30pm 6:30pm Team Meeting prep for Client 4+
2-15 4:20pm 6:26pm Met with kevin for an hour 6+
Week 6 Emails 1 hour various emails dealing with Client on the purchase of premium theme 7+
Week 7 Emails 2 hours Dealt with issues getting the premium theme and communication when client missed regular meeting 9 +
2-18 5:00 pm 7:00 pm meet with Kevin for scheduled meeting Client could not make it
2-21 4:30 pm 7:00 pm Looked over client provided rescources over week. Found premium theme issue.
2-23 4:00 pm 6:00 pm Presentation meeting, meet with Kevin Afterward 15+
2-24 5:00 pm 6:50 pm Prepped for client meeting , outlined goals for Milestone 1 17.8+
2-26 12:30pm 1:30 pm Went over Mayfirst people link that tony sent over to me 18.8+
2-26 1:30 pm 3:30 pm Worked on Website on Cloud 9 20.8+
2-27 1:30 om 4:00 pm MileStone Crunch / Sketched APP blueprint 23.3 +
2-28 2:00 pm 5:30 pm Milestone Presentation prep and Meeting 26.8 +
3-3 5:30 pm 7:00pm Weekly Meeting with Client 28.3 +
3-8 6:00 pm 7:00 pm Resolved admin authentication issue 29.3
3-8 11:00 pm 12:00 pm Research Premium theme website 30.3
3-9 5:00 pm 7:00pm Prepped for weekly meeting 32.3
3-14 8:00 pm 10:40pm Worked on Application Form and Created a new git branch 35.9 Hours
3-15 8:00 pm 9:10 pm Drafted email and worked on future planning while occupied with other things 36.4 Hours
January week 1-3 adding into new system 50.9 Hours
3-16 4:30pm 6:00pm Weekly meeting and updated the rest of the team on wordpress issues. 52.4 Hours
3-19 1pm 3pm 54.4 Hours
3-20 3 pm 5:30pm 56.9 Hours
3-21 8pm 9 pm 58 Hours
3-22 6-8/ 10-11 61 Hours
3-24 5:30 6:30 62 Hours
3-31 5:30 7:00 63.5
4-1 5:30 6:50 Attempted to Test Email Functions. Started shiftin site from C9 to local Host 64.5
4-2 6:00 9:30 67.5 Hours
4-5 2:00 2:30 Worked wth Nesh in getting server on Esos
4-5 6:00pm 8:25 Established MEails to work on local Branch

|

Week 1

Week 2

Week 3 Sunday ~40 mins

Started googling wordpress tips and tricks. Did a bit of content management of the wiki, sent confirmation emails confirming meeting on Tuesday. Started parsing through the online books on oracle.

Monday Meeting with Englesma 4:00- 5:10

Etched out and scoped a bit more of what our deadline would be for next week.

Tuesday Review Englesma's Critique of our Prospectus 10 min

Prepped for 6:00 meeting with client. 40 min

Set up feature request page on the wiki. 10

Weekend Week 4 Established new meeting time with Client Thursdays at 6PM Spent around 3 Hours over Saturday and Sunday reading Wordpress sites and getting cloud 9 IDE up and running. Looked over the how I spent time on this process and resolved to have a better system in tracking my progress.

Monday 4-7pm Working from home, established very rough outline for design document and continued getting the cloud 9 IDE up and running. Did peer reviews 20(min) Found the browser within the safari browser blocks the virtual wordpress account from working.