Manual dependencies - Profitbase/PowerBI-visuals-Gantt GitHub Wiki
Instead of setting up dependencies in your dataset, you can define task connections interactively directly on the Gantt chart using the built-in Task Information workspace.
How to Add Dependencies Manually
Step 1: Open the Task Information menu
Double-click any taskbar directly on the timeline to open the interactive Task Information popup menu.
Step 2: Configure the dependency relationship
- Click on the Dependency tab at the top of the menu.
- Select the task you want to link from the predecessor dropdown menu.
- Select the connection type (such as Finish-to-Start or Start-to-Start).
- Save your configuration.
Step 3: View the connector line
Once saved, the visual will draw a dependency connector line on the timeline linking the predecessor task to the selected task.