Baseline formatting (Planned start end date) - Profitbase/PowerBI-visuals-Gantt GitHub Wiki
Adding date fields to the Planned Start Date and Planned End Date data buckets adds a baseline to your tasks, allowing you to compare your original project schedule against actual progress.
1. Baseline Features and Requirements
Thinner Bar Display
The baseline is illustrated as a thinner bar (defaulting to an orange-brown shade) drawn directly underneath each actual taskbar so you can see schedule differences at a glance.
Requires Both Fields
Baseline bars will only appear on the timeline if both the Planned Start Date and Planned End Date buckets are filled. If either is left empty, the baseline bar will not display.
Baseline Tooltips
Hovering your mouse cursor over a baseline bar in the chart displays a tooltip showing the task's planned start date, finish date, and duration.
Child Tasks Only
Baselines are shown only on individual task rows. They do not summarize or combine into parent grouping rows.
2. Formatting Options
Under the Baselines card in the Format pane, you have the following controls to style your baselines:
Fill Color
Sets the interior color of the baseline bar. If not set, it defaults to the standard orange-brown shade.
Border Color
Sets the color of the thin outline around the baseline bar to help it stand out against the background and actual taskbars.
Reset to Default
Instantly clears all custom colors in this card and restores the default styling.