Sprint Retrospectives - OtagoPolytechnic/Cloudy-with-a-Chance-of-LoRa GitHub Wiki

Sprint Retrospective 1

Date:20/03/25

1. Review Sprint Goal

  • Learning LoRa
  • Becoming familiar with the project
  • Figuring out what works
  • Redesigns

2. What Went Well?

  • Almost got LoRa done
  • Both redesigns are done
  • Team work and good communication

3. What Could Be Improved?

  • Having someone able to work on both sides and help out
  • Using own branches

4. Action Items

  • Make Dev branch
  • Use Milestones
  • Keep on top of Kanban

Sprint Retrospective 2

Date:07/04/25

1. Review Sprint Goal

  • Individual progress has been made
  • Difficulties have been addressed

2. What Went Well?

  • Communication is going well
  • LoRa is on track to be finished
  • Research has been going well
  • Fixing the Wiki

3. What Could Be Improved?

  • Drop active issues into the teams chat so people can contribute more
  • Document things that aren't going well so people can help and we don't run into the same problems in the future
  • Changing focus has been taking up time
  • We need to look at scope of issues before taking them on

4. Action Items

  • Start working on codebase
  • Hopefully make a start with hardware
  • Next sprint starts in term 2