6b. Report Week 8 (July 20th to July 26th) - Maureque/GSoC2020-topology-osgeo-gvsig GitHub Wiki
Period.
- July 20th to July 26th
Report.
-
What did I complete this week?
- Developed action Mark Line Action. This action makes a new layer with red lines marks which corresponds to the lines selected in the error report. The action marks the errors in a clear visual way, then the user must choose what to do with them.
- Test and debug the developed code.
- Test and document existing code more thoroughly.
- Improvements in the rule of the week 5: “Must not have gaps”.
- Weekly report.
-
What am I going to achieve for next week?
- Topological rule: Must not intersect (line).
- Analyze, design and develop required Classes.
- Analyze, design and develop interactions with data sources.
- Finish documenting everything done with the rule Must Not Have Gaps.
- Weekly report.
-
Is there any blocking issue?
No, there is no blocking issue.