Daily Scrum Meeting Summary 1 ( Sprint 2 ) - JU-CSE-27/swe-wiki GitHub Wiki
Scrum Summary
Date/Location: 11-January-2022, Google Meet
Frequency: Daily
Meeting length: 20 minutes
MIM
Daily Task Progress:
1. Analysis on creating user profile is on going but not completed yet. bugs on
product sorting page are fixed and integrated with main project
Impediments:
1. Found some bugs(system was not redirecting proper html template during
sorting) but it is solved later
IJM
Daily Task Progress:
i. Analysis on product offer method is completed
Impediments:
1. Didn't found any issue.
TH
Daily Task Progress:
1. Analysis on creating live chat facilities and new events creating but not completed yet.
Impediments:
1. Found some bugs in creating live chatting and creating new events.
RRS
Daily Task Progress:
1. Analysis on payment method not completed.
Impediments:
1. Found some issues in integrating SSLCommerge and dependency on shopping cart.
TTP
Daily Task Progress:
1. Analysis of the product search method is ongoing but not completed yet. Bugs on
blog post adding page are fixed and integrated with the main project
Impediments:
1. Found some bugs to integrate the blogging app with the main project.
MSA
Daily Task Progress:
1. Analysis on creating shopping cart started. Some problems with fetching data from DB.
Impediments:
1. Generated some errors while linking with Database, working on it.