Retrospectives - J-Jullaphong/b2d-ventures GitHub Wiki
Iteration 1 ( 3 Sep 2024 )
Attendees: Jullaphong, Pichayanon, Kanisorn
What went right?
- Communication: We had a great communication between the members.
- Team Work: We did a nice job working together as a team. The workflow was smooth.
What went wrong?
- Time Management: The registration form took longer than what we expected.
- Minor Bugs: We faced some minor bugs during the development.
What to improve?
- Pair Programming: Pair programming was not effectively applied during the workflow, as each member also has their own works as well.
Iteration 2 ( 17 Sep 2024 )
Attendees: Jullaphong, Pichayanon, Kanisorn
What went right?
- Ahead of Schedule: We successfully completed all tasks ahead of the deadline.
What went wrong?
- None Notable Error: In this iteration, we faced little to no errors or obstacles.
What to improve?
- Maintaining Smooth Workflow: After such an exceptional iteration, we can focus on fine-tuning our processes to maintain or further enhance the current workflow.
Iteration 3 ( 1 Oct 2024 )
Attendees: Jullaphong, Pichayanon, Kanisorn
What went right?
- All Tasks Completed on Time: Despite challenges, all tasks for this iteration were completed as expected and delivered within the sprint timeline.
What went wrong?
- Midterm Exam Impact: The midterm examination week caused slight delays in task progress. We underestimated the impact of exams on our availability and work pace.
What to improve?
- Improved Task Scheduling: The scheduling during exam week was less accurate due to an underestimation of time and workload management. By factoring in potential external risks, such as exams, we can improve our planning and avoid disruptions to the workflow.
Iteration 4 ( 15 Oct 2024 )
Attendees: Jullaphong, Pichayanon, Kanisorn