Team Capacity & Sprint 2 Effort Estimation - Hinduino/CareerConnect GitHub Wiki
The team utilizes the Fibonacci sequence for estimating the relative effort, complexity, and risk of each user story and task. One Story Point equates to approximately 1 hour of focused effort.
Total Sprint 2 Capacity:
- Team Size: 5 active members
- Sprint Duration: ~3.5 Weeks (October 4 – October 26)
- Total Available Capacity: ~79 Story Points (Hours)
Sprint 2 Task Breakdown & Point Allocation:
-
Core Job & Recruiter Features (23 Points)
- Implement the Job Search & Job Listing Interface (5 Points)
- Job application submission & tracking (8 Points)
- Recruiter Dashboard and Posting Management (8 Points)
- Fix Recruiter Dashboard Unit Test Failure (2 Points)
-
User & Authentication Updates (10 Points):
- Develop User Profile and Resume Management (5 Points)
- Enhance user registration and login validation (5 Points)
-
AI & New Features (5 Points):
- Implement the AI Chatbot (5 Points)
-
System Integration & Codebase Maintenance (10 Points):
- UI, Database & Server Integration Updates (5 Points),
- Cleanup codebase (2 Points)
- Fix connection issue between Server and Frontend (1 Point)
- Fix database issue (1 Point), and Fix environment (1 Point)
-
Quality Assurance & Testing (16 Points):
- General test implementation (8 Points)
- Test whole sprint 2 implementations (8 Points)
-
Sprint Administration & Documentation (15 Points):
- Create and link GitHub user stories and assigned tasks (5 Points)
- Update the project board, backlog, sprint plan, and task assignments (5 Points)
- Update AI usage logs and validation evidence (2 Points)
- Complete individual contribution logs with time spent and evidence links (2 Points)
- Compile and submit the one-page Sprint 2 Summary Report (1 Point)
-
Total Planned Effort: 79 Points.