Team Capacity & Sprint 2 Effort Estimation - Hinduino/CareerConnect GitHub Wiki

The team utilizes the Fibonacci sequence for estimating the relative effort, complexity, and risk of each user story and task. One Story Point equates to approximately 1 hour of focused effort.

Total Sprint 2 Capacity:

  • Team Size: 5 active members
  • Sprint Duration: ~3.5 Weeks (October 4 – October 26)
  • Total Available Capacity: ~79 Story Points (Hours)

Sprint 2 Task Breakdown & Point Allocation:

  • Core Job & Recruiter Features (23 Points)

    • Implement the Job Search & Job Listing Interface (5 Points)
    • Job application submission & tracking (8 Points)
    • Recruiter Dashboard and Posting Management (8 Points)
    • Fix Recruiter Dashboard Unit Test Failure (2 Points)
  • User & Authentication Updates (10 Points):

    • Develop User Profile and Resume Management (5 Points)
    • Enhance user registration and login validation (5 Points)
  • AI & New Features (5 Points):

    • Implement the AI Chatbot (5 Points)
  • System Integration & Codebase Maintenance (10 Points):

    • UI, Database & Server Integration Updates (5 Points),
    • Cleanup codebase (2 Points)
    • Fix connection issue between Server and Frontend (1 Point)
    • Fix database issue (1 Point), and Fix environment (1 Point)
  • Quality Assurance & Testing (16 Points):

    • General test implementation (8 Points)
    • Test whole sprint 2 implementations (8 Points)
  • Sprint Administration & Documentation (15 Points):

    • Create and link GitHub user stories and assigned tasks (5 Points)
    • Update the project board, backlog, sprint plan, and task assignments (5 Points)
    • Update AI usage logs and validation evidence (2 Points)
    • Complete individual contribution logs with time spent and evidence links (2 Points)
    • Compile and submit the one-page Sprint 2 Summary Report (1 Point)
  • Total Planned Effort: 79 Points.