MEGA 2.0 Kickoff - Gepardec/mega GitHub Wiki

Mega 2.0 Team

  • Werner
  • Stefan
  • Robin
  • Rainer
  • Christoph R
  • Julian
  • Thomas
  • Mario A.

Agenda

  • Vision, Aims & Constraints
    • Constraints
      • Tooling
        • GitHub (does not contain WIPs -> SM checks WIP Limits)
  • MEGA 2.0 Organisation
    • Kanban instead of SCRUM
      • no sprint commitments - you finish an issue; you pull the next one from the backlog
      • we estimate stories nonetheless (to get to a common understanding of the issue)
    • commitment
      • how much time can everybody dedicate to the project?

        • 20 weeks -> 110 hrs (excluding illnesses, holidays, other LF projects)
      • Alternatives: GitLab; Codegiant; Atlassian; Zube

    • What meetings do we want to hold?
      • reviews (what intervals?)
      • retrospectives (in intervals or only when needed?)
      • dailies/weeklies
    • DoR & DoD
    • how do we want to work in this project?
      • How do we organize our work time? More camps? Indiviuals work on their own?
      • do we need and who wants to be DEV lead?
      • do we need and who defines coding guidelines?
      • schedule
        • start of project date: 10.07.2020
        • end of project date: 04.12.2020
    • roles in our team
      • Werner - PO
      • Stefan - SM / RE-Coach
      • UXD?
  • Bootcamp
    • first bootcamp is set for July 16./17.
  • Refinement
    • Do we remedy the media break first and then refine the single steps?
    • Planning - prepare the first few User Stories for work
    • are there any new technical constraints? db, APIs, ...