Week 1 Log

Date Task Description IC / OC Time Spent (min)
8/26/24 confirmed with teammate to continue project OC 20
8/28/24 Went through ideas for further development OC 30
8/30/24 tested app and fixed bug with outdated Gemini API key IC 30
9/03/24 Made a shared document and noted down the steps for sprint 1. OC 30

Week 2

Date Task Description IC / OC Time Spent (min)
9/04/24 buddy team feedback IC 45
9/06/24 planning for the release 1 demo & Updated the github wiki IC 45
9/09/24 work on sprint 3, divided/planned tasks for release 1 IC 45

Week 3

Date Task Description IC / OC Time Spent (min)
9/09/24 met on zoom for task planning IC 45
9/11/24 work on developing demo IC 45
9/13/24 work on developing demo OC 90

Week 4

Date Task Description IC / OC Time Spent (min)
9/16/24 coding for demo OC 45
9/17/24 coding for demo & creating slides OC 80
9/18/24 presented demo IC 5
9/18/24 project planning for next sprint; retrospective & evaluation IC/OC 50
9/20/24 continue sprint planning OC 20

Week 5

Date Task Description IC / OC Time Spent (min)
9/23/24 Worked on the gooey api fixing IC 45
9/25/24 Working on aligning the gemini and gooey setup in the abstraction layer IC 45
9/27/24 Figure out the gooey generation issue, fixed the git merging issue IC 45
9/29/24 finalize gooey fixes OC 30

Week 6

Date Task Description IC / OC Time Spent (min)
9/30/24 test Gooey and consider alternative AI tools IC 45
10/2/24 Work on app UI IC 45
10/4/24 Work on app UI IC&OC 90
10/6/24 Finalize UI, create release 2 artifacts OC 90

Week 8

Date Task Description IC / OC Time Spent (min)
10/21/24 Research database/login backends IC 45
10/23/24 continue research, ER diagramming IC 45
10/25/24 Select & begin supabase work IC&OC 90

Week 9

Date Task Description IC / OC Time Spent (min)
10/28/24 continue supabase work IC/OC 90
10/29/24 continue supabase work OC 45
10/30/24 continue supabase work IC 45
11/1/24 debugging gemini error IC 45

Week 10

Date Task Description IC / OC Time Spent (min)
11/4/24 debugging expo errors IC 45
11/6/24 debugging expo errors IC/OC 165
11/8/24 debugging expo IC 45

Week 11

Date Task Description IC / OC Time Spent (min)
11/11/24 debugging expo IC 45
11/13/24 expo updated, more debugging IC 45
11/14/24 expo updated, more debugging OC 90
11/15/24 expo debugging IC 45

Week 12

Date Task Description IC / OC Time Spent (min)
11/17/24 debugging expo OC 80
11/18/24 App UI changes, presentation artifacts OC 90
11/22/24 app UI & dream log fixes IC 45