Meeting Notes
Attendance:
villarre
shariatz
yliu30
prabhnoo
dennea
jgerun
Goals:
Figure out on how to distribute the work for project part 3 haly-way checkpoint.
The Backlog file is completed with a story size and risk level evaluation on each story.
The work distribution is decided and recorded in this meeting log.
Discussion log:
Initialize the project: shariatz
DB set up: dennea
JUnit set up: yliu30
US 01.01.01: villarre & shariatz
US 01.02.01: villarre
US 01.03.01: prabhnoo
US 01.04.01: jgerun
US 01.05.01: shariatz
US 01.06.01: dennea & jgerun & yliu30
US 02.01.01: dennea & villarre
US 02.02.01: prabhnoo & yliu30
US 02.03.01: yliu30
US 02.04.01: jgerun
US 02.05.01: dennea & jgerun
US 02.06.01: yliu30
US 02.07.01: dennea & villarre
US 02.08.01: shariatz & prabhnoo
Team members who are responsible for a whole part of user stories (e.g. Ingredients) should work closely together, so that each of those user stories would have greater consistency.