Members:


  • Anni
  • Bicheng
  • Liwen
  • Jingjing
  • Xiaocong

Notes:


  • Group problems:

    • Because we do not have enough net work in the group, all parts of the project part 2 can hardly be merged.

      • We need more group meetings, and teamwork.
    • We did not finish the 2nd part of the project in last week.

      • The deadline of part 2 is coming, we need to finish this part in 2 days.
      • Big problem: all members have 2 or more mid term exams this week.
      • Need to plan the time schedule well.

  • Individual problems:

    • Some of the pictures in the storyboard is not easy and clear enough ( from the manager's feedback).

      • Xiaocong need to re-design some parts of the storyboard
    • The UML and SSD have not been designed and posted.

      • Liwen need to finish the UML and SSD as soon as possible
      • Steps:
        • 1-since Anni completed the basic code structure before UML, Liwen should read through the existed class and activities.
        • 2-based on the current structure and use cases, design and modify the UML and SSD.
        • 3-all member must come and meet at Oct 17 to unify ideas, and help Liwen on the UML and SSD
    • The current Junit tests should consider more conditions

      • Bichng need to re-design some of the Junit tests to handle all conditions in use cases.
    • The current structure may need a controller and need to be simplified

      • Anni need to modify the structure and to simplify classes and activity.
    • Project Glossary and use cases must be done as soon as possible

      • Jingjing will do this after her 379 midterm.

Current Goal: complete project part 2 before deadline!!

Next Meeting on this Friday!!!

Next Topic: assign work for part 3, coding style, use cases to implement, time management.


Fin