3/4/14 - 3/11/14
Hardware
Build LNA and FeedTest controller and motor with srtnUpdate wiki with parts pictures and general project info.
Software
Beef up documentation for code where possible
--
3/11/14 - 3/18/14
Hardware
- Prep for roof build ->
test rotor, figure out dish location, figure out dish construction logistics
Software
Continue to build up documentation for code where possible
--
3/18/14 - 3/25/14
Hardware
Build Feed- Test Roof for RF interference once feed is completed (if needed, move to week of 3/25/14)
Request for roof access for Friday 3/21 at 3 pm -- Goal: Test for RF interference and verify telescope placement (if needed, move to week of 3/25/14)For placement of dish remember to think about having unblocked trees nearby for calibration, make sure we can drill through roof for cables
Software
Continue documenting codeGet rotator to work via USB
--
3/25/14 - 4/1/14
Hardware
If tasks from last week not complete:
- Test Roof for RF interference
- Verify dish placement
- Request for room access Tuesday 3/25/14 2 pm
- Decide which mount style we will use
If tasks from last week complete:
- Decide which mount style we will use
- Assemble dish base and dish
Software
- Make centralized config file(s)
Put all constants into a constants file, all files should reference constants fileImprove documentation as progress is made- Improve naming conventions
--
4/1/14 - 4/8/14
Hardware
If tasks from last week not complete:
- Build base and dish
If tasks from last week complete:
- Mount Dish -- Request for roof access Tuesday 4/1/14 2 pm
- Decide where we need to modify roof for running cables
Software
- Begin to separate out UI from back-end
Improve documentation and all help files- Improve naming conventions
--
###REVISED WORK SCHEDULE BELOW
4/8/14 - 4/15/14 (Long Weekend)
Hardware
If tasks from last week not complete:
- Mount Dish -- request for roof access Tuesday 4/18/14 2 pm
- Decide where to make roof mods
If tasks from last week complete:
- Make modifications to roof
- fire it up
Software
- Improve documentation
- Clean srt.cat file, document, make examples
- Improve help file
- Add comments to code, where possible
- Continue testing on various OS/Architectures, make a table detailing which work, and what they need to work
- Centralized config file?
- Assess and start fixing bugs (error handling also) for known issues
--
4/15/14 - 4/22/14
Hardware
If tasks from last week not complete:
- make roof mods
- fire it up
Software
- Continue with bug fixes
- Continue improving documentation
- If time, start looking into optional issues (enhancements)
--
4/22/14 - 4/29/14
Hardware
- Troubleshoot, make fixes/mods as needed
- Full test of telescope capabilities -- make sure full az/el movement is possible, make sure signal is strong enough for observing
Software
- Continue with bug fixes
- Continue improving documentation
- If time, start looking into optional issues (enhancements)
- Create a makefile/installer for srtn so all package dependencies and whatnot are taken care of
- Calibration? (dependent on our results from observing?)
--
4/29/14 - 5/6/14
Software
- Continue with bug fixes
- Continue improving documentation
- Separate out logic from GUI
- Improvements to GUI?
- Calibration? (dependent on our results from observing?)
--
5/6/14 - 5/13/14
Software
- Continue with bug fixes
- Work on enhancements if time
- Try to port to other OS'es
--
5/13/14 - 5/20/14
Software
- Continue with bug fixes
- Work on enhancements if time
- Try to port to other OS'es