3/4/14 - 3/11/14

Hardware

  • Build LNA and Feed
  • Test controller and motor with srtn
  • Update wiki with parts pictures and general project info.

Software

  • Beef up documentation for code where possible

--

3/11/14 - 3/18/14

Hardware

  • Prep for roof build -> test rotor, figure out dish location, figure out dish construction logistics

Software

  • Continue to build up documentation for code where possible

--

3/18/14 - 3/25/14

Hardware

  • Build Feed
  • Test Roof for RF interference once feed is completed (if needed, move to week of 3/25/14)
  • Request for roof access for Friday 3/21 at 3 pm -- Goal: Test for RF interference and verify telescope placement (if needed, move to week of 3/25/14)
  • For placement of dish remember to think about having unblocked trees nearby for calibration, make sure we can drill through roof for cables

Software

  • Continue documenting code
  • Get rotator to work via USB

--

3/25/14 - 4/1/14

Hardware

If tasks from last week not complete:

  • Test Roof for RF interference
  • Verify dish placement
  • Request for room access Tuesday 3/25/14 2 pm
  • Decide which mount style we will use

If tasks from last week complete:

  • Decide which mount style we will use
  • Assemble dish base and dish

Software

  • Make centralized config file(s)
  • Put all constants into a constants file, all files should reference constants file
  • Improve documentation as progress is made
  • Improve naming conventions

--

4/1/14 - 4/8/14

Hardware

If tasks from last week not complete:

  • Build base and dish

If tasks from last week complete:

  • Mount Dish -- Request for roof access Tuesday 4/1/14 2 pm
  • Decide where we need to modify roof for running cables

Software

  • Begin to separate out UI from back-end
  • Improve documentation and all help files
  • Improve naming conventions

--

###REVISED WORK SCHEDULE BELOW

4/8/14 - 4/15/14 (Long Weekend)

Hardware

If tasks from last week not complete:

  • Mount Dish -- request for roof access Tuesday 4/18/14 2 pm
  • Decide where to make roof mods

If tasks from last week complete:

  • Make modifications to roof
  • fire it up

Software

  • Improve documentation
    • Clean srt.cat file, document, make examples
    • Improve help file
    • Add comments to code, where possible
  • Continue testing on various OS/Architectures, make a table detailing which work, and what they need to work
  • Centralized config file?
  • Assess and start fixing bugs (error handling also) for known issues

--

4/15/14 - 4/22/14

Hardware

If tasks from last week not complete:

  • make roof mods
  • fire it up

Software

  • Continue with bug fixes
  • Continue improving documentation
  • If time, start looking into optional issues (enhancements)

--

4/22/14 - 4/29/14

Hardware

  • Troubleshoot, make fixes/mods as needed
  • Full test of telescope capabilities -- make sure full az/el movement is possible, make sure signal is strong enough for observing

Software

  • Continue with bug fixes
  • Continue improving documentation
  • If time, start looking into optional issues (enhancements)
  • Create a makefile/installer for srtn so all package dependencies and whatnot are taken care of
  • Calibration? (dependent on our results from observing?)

--

4/29/14 - 5/6/14

Software

  • Continue with bug fixes
  • Continue improving documentation
  • Separate out logic from GUI
  • Improvements to GUI?
  • Calibration? (dependent on our results from observing?)

--

5/6/14 - 5/13/14

Software

  • Continue with bug fixes
  • Work on enhancements if time
  • Try to port to other OS'es

--

5/13/14 - 5/20/14

Software

  • Continue with bug fixes
  • Work on enhancements if time
  • Try to port to other OS'es