Iteration 2 - BackEndByAlex/Timelock GitHub Wiki
Sprint Backlog v1 – Reflection
During this sprint I did much more than just coding. I read about requirements, testing and how to work agile. I set up all three applications (auth, password and frontend), installed important packages and created a good structure for each part. It was a bit tricky to get everything to talk to each other. I also worked with the vision, risk list, backlog. It became more work than I thought.
✅ - completed
❌ - not completed
Task | Requirement | Test Status | Estimated Time | Actual Time |
---|---|---|---|---|
Chapters 5,6,7 | Design and Modeling read | ✅ | 11 | 6 |
Product backlog | Continue working to fill out | ✅ | 2 | 2 |
Work away previous risks | Related risk: Various risks | ✅ | 1 | 1 |
Start implementation | Code Structure, implement a view | ✅ | 10 | 10 |
Design a test plan | how the application should be tested; test tools, test frameworks etc. | ✅ | 1 | 1 |
New sprint backlog, Test report 2 | week 3 | ✅ | 1 | 1 |
Working in projects | Video recording check | ✅ | 2 | 2 |
Introduction to containers | Study/compare with previous knowledge | ✅ | 2 | 1 |
JTI - Docker | Study | ✅ | 2 | 2 |
Introduction to software architecture | Study | ✅ | 2 | 2 |
Standup | Participate/Discuss | ✅ | 2 | 2 |
Group work | Present, backlog, remaining, planning, prepare group presentation | ✅ | 6 | 6 |
Sum | 42 | 36 | ||
Time since previous iteration | 55 | 66 | ||
Total time in project | 97 | 102 |