1. User authentication complete with signup and login (5 days)
- Signup Form (1 day)
- Login Form (1 day)
- Database schema (1 day)
- Routes and backend logic (3 days)
2. Full CRUD (w/out images) (11 days)
- Creation form (2 days)
- Database schema (1 day)
- Backend routes and logic (2 days)
- Index page (2 days)
- Index page integration (1 day)
- Show page (2 days)
- Show page integration (1 day)
3. Image uploading (6 days)
- Learn about hosting on AWS S3 (2 days)
- Add upload functionality to form (1 day)
- Database schema (1 day)
- Backend logic (2 days)
4. Filter (5 days)
- Database schema (1 day)
- Backend logic (2 days)
- Add filter functionality to show page (1 day)
- Build the filter index page (1 day) // should be same ItemsList component as index page