Backend-first implementation roadmap

Planning baseline: 2026-09-28; delivery cadence revised on the same date. P01-T01…T12 are implemented with prior local validation evidence; remote acceptance remains to be verified. The Android baseline was subsequently successful, as recorded in BASELINE_VALIDATION. Do not restart completed foundation work from the initial planning status.

How to execute

Start with P01-T13 to activate the newly adopted delivery workflow, then resume P02. Read AGENTS, FAST_EXECUTION, current PROGRESS, and only the chosen task plus relevant inputs. DELIVERY_WORKFLOW and CI_PLAN own execution cadence. Existing workflows remain binding until G01-FLOW; new commands are not available merely because the plan names them.

There are 78 tasks across 11 phases. P01-T01…T12 are LOCAL_DONE based on preserved evidence; all new P01-T13…T17 and P02…P11 tasks are NOT STARTED. MUST is the bounded MVP, LATER is separately validated paid scope. Split an oversized task into letter-suffixed IDs before implementation. One task at a time does not mean one PR per task: one phase branch/draft PR contains its task commits. A requested phase can proceed sequentially without redundant per-task approval. No agent delegation is implied.

Validation has three levels: targeted task/risk checks now; specialized phase exit plus quick local/remote checks for integration; full certification on an immutable release candidate after the required phase merges. Explicitly required DB/auth/restore/load acceptance tests remain immediate when their task is implemented. No known failure or critical test may be deferred. Detailed task commands state what must be proven; CI_PLAN prevents redundant whole-project reruns without weakening that proof.

Hard dependency: P10 Android improvements start only after G09 RELEASE_CERTIFIED. Existing Android regression tests may run earlier. P01–P08 can integrate without claiming a release; P09 certifies the complete backend/infra. Accounts/billing/sync are outside backend MVP completeness.

DOD-1 in AI_ENGINEERING_CONTRACT means local task acceptance; phase integration and release certification are separate. Publish one issue/task and milestone/branch/PR per phase within authorized delivery scope; close issues through the verified phase merge; mirror docs to wiki once per merged phase, recording any WIKI_PENDING retry separately. Phase record template keeps evidence reusable and current state short.

Phase order

P00 import/audit/planning β†’ P01 foundations + G01-FLOW delivery activation β†’ P02 official catalog β†’ P03 identity/jobs β†’ P04 observations β†’ P05 evidence β†’ P06 trust/consensus β†’ P07 moderation/privacy β†’ P08 infrastructure/hardening β†’ P09 backend release gate β†’ P10 Android β†’ P11 optional commercial services.

Elapsed dates and total cost are deliberately not promised before prerequisite, parser/geocoder and load evidence. Sequence by dependencies, not invented calendar deadlines.

P01 β€” Backend foundations

Priority: MUST. Entry: No earlier implementation gate; planning baseline exists..

Exit gate: G01: documented prerequisite report; Go build/unit/static checks; typed config; health/lifecycle; real local PostGIS; migrations from empty; image build and CI; base OpenAPI lint. Android baseline blockers are recorded and resolved before G09.

P01-T01 β€” Prerequisites and inherited baseline

  • ID / priority / status: P01-T01 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Reproduce the imported Android baseline and pin a supported backend toolchain plan.
  • Why: Avoid building on an unverified environment.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; docs/planning/BASELINE_VALIDATION.md; docs/tech-stack.md.
  • Files/areas expected: docs/planning/BASELINE_VALIDATION.md; docs/backend/TOOLCHAIN.md; scoped legacy documentation (area list, not a literal combined path).
  • Dependencies: No earlier implementation gate; planning baseline exists.; all earlier phase gates.
  • Tests first: Verify JDK 17/SDK 35 availability and current Gradle command failures before remediation.
  • Implementation outline: Provision execution prerequisites without changing Android versions; verify Go/Docker/Compose; record version/license/support choices and A01/A02/A11 documentation corrections.
  • Acceptance criteria: Baseline commands have exact outcomes; no false green; Go/PostGIS/tool choices recorded.
  • Validation commands: java -version; go version; docker version; docker compose version; ./gradlew :domain:test :application:test :data:testDebugUnitTest :app:testDebugUnitTest :app:assembleDebug --no-daemon. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Missing workstation SDK or daemon access is an environment blocker.
  • Rollback/Recovery: Revert documentation/tool setup in its own scope; do not rewrite Gradle/source to bypass failures.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T02 β€” Go module and process roots

  • ID / priority / status: P01-T02 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Create minimal compilable API/worker/migrator entry points.
  • Why: Establish one codebase and build boundary.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; backend/README.md; ADR-005.
  • Files/areas expected: backend/go.mod; backend/go.sum when needed; backend/cmd/* (area list, not a literal combined path).
  • Dependencies: P01-T01; all earlier phase gates.
  • Tests first: Build empty entry points and verify no Android dependency.
  • Implementation outline: Choose module path for new repository, supported pinned Go version and minimal roots without business code.
  • Acceptance criteria: Three commands compile; no speculative business packages.
  • Validation commands: cd backend && go test ./... && go build ./cmd/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Premature frameworks and dependency sprawl.
  • Rollback/Recovery: Revert unshipped module files.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T03 β€” Typed startup configuration

  • ID / priority / status: P01-T03 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Validate configuration once at process startup.
  • Why: Prevent half-configured production processes.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN; SECURITY_PRIVACY.
  • Files/areas expected: backend/internal/platform/config; backend/.env.example; narrow .gitignore exception (area list, not a literal combined path).
  • Dependencies: P01-T02; all earlier phase gates.
  • Tests first: Missing/invalid environment, DSN and limit values fail safely; secrets never print.
  • Implementation outline: Implement typed parsing/defaults/environment modes; inject config into roots.
  • Acceptance criteria: Fail-fast errors are redacted; sample contains no secrets.
  • Validation commands: cd backend && go test ./internal/platform/config/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Overpermissive defaults accidentally enable production mode.
  • Rollback/Recovery: Revert config changes; keep old startup path until tests pass.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T04 β€” Structured logging and redaction

  • ID / priority / status: P01-T04 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Add slog factory and request/job context.
  • Why: Make failures diagnosable without personal payloads.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; SECURITY_PRIVACY; B-BR-011.
  • Files/areas expected: backend/internal/platform/telemetry (area list, not a literal combined path).
  • Dependencies: P01-T03; all earlier phase gates.
  • Tests first: Assert body, GPS, tokens and URLs absent from representative logs.
  • Implementation outline: Expose bounded fields/redaction helpers and injected sinks.
  • Acceptance criteria: JSON records include request ID, role and stable code only.
  • Validation commands: cd backend && go test ./internal/platform/telemetry/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Secret leakage or high-cardinality fields.
  • Rollback/Recovery: Revert logger adapter and rotate any accidentally exposed real secret if incident occurs.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T05 β€” HTTP lifecycle

  • ID / priority / status: P01-T05 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Implement bounded HTTP server and graceful shutdown.
  • Why: Avoid leaked requests/connections during deploy.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; TARGET_ARCHITECTURE; API_PLAN.
  • Files/areas expected: backend/internal/platform/httpserver; backend/cmd/api (area list, not a literal combined path).
  • Dependencies: P01-T04; all earlier phase gates.
  • Tests first: httptest shutdown/cancellation and oversized/slow request cases.
  • Implementation outline: Wire chi, timeout/body-limit middleware and signal-aware drain.
  • Acceptance criteria: Server starts/stops predictably; no business rules in middleware.
  • Validation commands: cd backend && go test ./internal/platform/httpserver/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Timeouts terminating accepted work incorrectly.
  • Rollback/Recovery: Rollback binary; ensure accepted jobs stay durable.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T06 β€” Liveness and readiness

  • ID / priority / status: P01-T06 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Separate process health from dependency readiness.
  • Why: Support safe routing without restart loops.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN.
  • Files/areas expected: backend/internal/platform/health (area list, not a literal combined path).
  • Dependencies: P01-T05; all earlier phase gates.
  • Tests first: Healthy process with failed DB is live but not ready; no config disclosure.
  • Implementation outline: Inject readiness checks; expose minimal status.
  • Acceptance criteria: Health semantics match plan under dependency failure.
  • Validation commands: cd backend && go test ./internal/platform/health/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: DB outage causing cascading restarts.
  • Rollback/Recovery: Revert routing/check config and restore previous health handler.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T07 β€” Local PostgreSQL/PostGIS service

  • ID / priority / status: P01-T07 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Add disposable Compose database with persistent named local volume.
  • Why: Enable real spatial integration tests.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; DATA_MODEL; INFRASTRUCTURE_PLAN.
  • Files/areas expected: infra/compose.dev.yml; infra/docker; infra/README.md (area list, not a literal combined path).
  • Dependencies: P01-T06; all earlier phase gates.
  • Tests first: Compose config validity, loopback binding and readiness probe.
  • Implementation outline: Pin compatible supported image/digest, dev-only credentials and volume names.
  • Acceptance criteria: Local DB boots; ports are not public; no production data involved.
  • Validation commands: docker compose -f infra/compose.dev.yml config; docker compose -f infra/compose.dev.yml up -d db. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Confusing disposable and persistent production volumes.
  • Rollback/Recovery: Stop only project local services; never remove production volumes.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T08 β€” Migration runner and PostGIS bootstrap

  • ID / priority / status: P01-T08 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Apply ordered SQL with lock/checksum ledger.
  • Why: Establish the only schema-change mechanism.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; DATA_MODEL.
  • Files/areas expected: backend/cmd/migrate; backend/internal/platform/migrate; backend/db/migrations (area list, not a literal combined path).
  • Dependencies: P01-T07; all earlier phase gates.
  • Tests first: Empty DB, second apply, checksum mutation and concurrent runner cases.
  • Implementation outline: Choose minimal maintained migration mechanism or explicit runner by dependency record; enable PostGIS under deployment role.
  • Acceptance criteria: PostGIS version query works; apply idempotent; checksum mismatch fails.
  • Validation commands: cd backend && go test -tags=integration ./internal/platform/migrate/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: DDL locks/role privilege mistakes.
  • Rollback/Recovery: For initial disposable DB recreate only local volume; future fixes append migrations.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T09 β€” Database pool and SQL tooling

  • ID / priority / status: P01-T09 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Set pgx pool limits and sqlc ownership structure.
  • Why: Keep SQL visible and connections bounded.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; DATA_MODEL; TARGET_ARCHITECTURE.
  • Files/areas expected: backend/internal/platform/database; backend/sqlc.yaml; backend/db/queries (area list, not a literal combined path).
  • Dependencies: P01-T08; all earlier phase gates.
  • Tests first: Connection timeout/cancellation and generated query smoke with real DB.
  • Implementation outline: Wire injectable transaction/pool ownership; generate minimal typed health query.
  • Acceptance criteria: Pool closed on shutdown; SQL generation reproducible.
  • Validation commands: cd backend && go test -tags=integration ./internal/platform/database/... && sqlc vet && sqlc generate. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Connection starvation and cross-module SQL leakage.
  • Rollback/Recovery: Rollback adapter config; preserve schema and accepted data.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T10 β€” API and worker images

  • ID / priority / status: P01-T10 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Build reproducible non-root process images.
  • Why: Make later deploys reviewable and recoverable.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN.
  • Files/areas expected: infra/docker; backend/.dockerignore; infra/README.md (area list, not a literal combined path).
  • Dependencies: P01-T09; all earlier phase gates.
  • Tests first: Build/run smoke with injected fake/dev config; inspect image for secrets.
  • Implementation outline: Use multi-stage pinned builders; same release provenance for roles.
  • Acceptance criteria: Images boot and terminate; no source secrets or build cache shipped.
  • Validation commands: docker build -f infra/docker/Dockerfile --target api .. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Leaking credentials into layers or mismatched role versions.
  • Rollback/Recovery: Discard unpromoted images and return to previous digest.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T11 β€” Base OpenAPI and golden vocabulary

  • ID / priority / status: P01-T11 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Encode base schemas/errors/security and contract checks.
  • Why: Freeze money/units/enums before handlers expand.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; API_PLAN; DOMAIN_MODEL.
  • Files/areas expected: contracts/openapi/v1.yaml; contracts/testdata/api; contract validator config (area list, not a literal combined path).
  • Dependencies: P01-T10; all earlier phase gates.
  • Tests first: Valid/invalid amount, unit, enum and error envelope vectors.
  • Implementation outline: Add common schemas, health/public API skeleton and auth profile references; pin linter.
  • Acceptance criteria: Contract parses/lints; examples validate; future endpoints added before code.
  • Validation commands: Run the pinned OpenAPI lint/example commands documented in contracts/README.md. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Contract without semantics or silently changed legacy names.
  • Rollback/Recovery: Revert unpublished schema change; never overwrite a published contract.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01-T12 β€” CI fast and full gate wiring (initial cadence; superseded by G01-FLOW)

  • ID / priority / status: P01-T12 / MUST / LOCAL_DONE (prior evidence; remote integration not reverified).
  • Goal: Create path-aware backend checks and improve secret coverage.
  • Why: Keep feedback fast without weakening release checks.
  • Inputs: docs/backend/TARGET_ARCHITECTURE.md, docs/backend/TEST_STRATEGY.md; TEST_STRATEGY; AI_ENGINEERING_CONTRACT.
  • Files/areas expected: .github/workflows; backend/README.md; scripts/check-* (area list, not a literal combined path).
  • Dependencies: P01-T11; all earlier phase gates.
  • Tests first: Deliberately malformed formatting/schema/secret fixture makes isolated gate fail.
  • Implementation outline: Pin actions/tools; unit/static/security fast job; PostGIS integration job; retain Android CI.
  • Acceptance criteria: CI checks cannot silently skip missing DB; docs edits avoid full Android rebuild.
  • Validation commands: Run the documented fast gate locally; inspect a CI run when branch is published. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: CI secrets on fork PRs; false-green skipped integration.
  • Rollback/Recovery: Revert workflow only; retain proven Android workflow.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P01 extension β€” Activate fast phase delivery before P02

Entry: foundation P01-T01…T12 exists; confirm its local evidence and actual repository state. G01-FLOW exits only when quick/full separation, safe branch/PR lifecycle, idempotent issue preparation, owned-page wiki preview and actual CI/protection migration are proven. Remote or wiki permissions unavailable mean an explicit pending operation, not an invented success. Wiki target unavailability can remain a recorded publication blocker if generated docs are valid; required CI/protection uncertainty blocks workflow activation and merge.

These are implementation tasks for the already delivered plan; this documentation edit does not mark them done. Use a new bounded phase-extension branch/PR and reuse existing completed foundation history. Remote phase publication requires the applicable session scope; LOCAL_ONLY can prepare/test all artifacts and previews without mutations.

P01-T13 β€” Separate local quick and release verification entry points

  • ID / priority / status: P01-T13 / MUST / NOT STARTED.
  • Goal: Make task, integration and release checks explicit and cheap to select.
  • Why: Prevent repeated full suites while preserving critical checks.
  • Inputs: CI_PLAN; TEST_STRATEGY; existing check-backend-fast.sh.
  • Files/areas expected: Makefile or equivalent small entry points; scripts/check-*; explicit check manifest; backend/README.
  • Dependencies: P01-T12; original foundation evidence; current session publication scope.
  • Tests first: Compile-only cannot claim tests; selected test filter executes cases; missing tool/unclassified change/secret in committed PR diff fails; docs-only checks meaningful.
  • Implementation outline: Build quick-verify and full verification composition from existing gates; retain targeted real PostGIS/race tasks; cache/pin tools; scanner/parser failures must propagate.
  • Acceptance criteria: Named entry points work; quick budget measured; full matrix remains complete; no product behavior change.
  • Validation commands: Run focused harnesses for gate selection/failure and one measured quick run; inspect full dependency graph, without running all release infrastructure here. Record the exact created executable commands and outcomes in the task evidence.
  • Risks: Masking errors or scanning only a clean working-tree status.
  • Rollback/Recovery: Keep current mandatory CI intact until T17 activates replacement.
  • Definition of done: DOD-1 local acceptance; G01-FLOW additionally needs T17 integration evidence. Do not claim publication/activation based on planning alone.

P01-T14 β€” Phase branch and PR lifecycle controller

  • ID / priority / status: P01-T14 / MUST / NOT STARTED.
  • Goal: Automate isolation, draft PR sync and guarded phase closure.
  • Why: Keep one commit per task and one PR per phase with no unsafe shortcuts.
  • Inputs: DELIVERY_WORKFLOW; template PHASE_RECORD; P01-T13.
  • Files/areas expected: scripts/git-flow.sh and its isolated tests; phase state/manifest.
  • Dependencies: P01-T13; original foundation evidence; current session publication scope.
  • Tests first: Wrong repo/main/dirty tree, missing required check, failed/skipped/cancelled check, changed head/base and unmerged-branch deletion all refuse; dry-run causes zero mutations.
  • Implementation outline: Implement start/sync/status/finish with trusted repo validation, quick local, named check identity and PR head/base binding, compare-and-swap merge and safe ancestry cleanup.
  • Acceptance criteria: Synthetic Git/fake GitHub lifecycle passes; missing authorization does not mutate; no full suite per task/phase.
  • Validation commands: Run shell syntax/static checks and fake-remote lifecycle tests; actual PR smoke belongs to T17. Record the exact created executable commands and outcomes in the task evidence.
  • Risks: Racing PR heads, accepting unknown status, deleting unrelated work.
  • Rollback/Recovery: Abort before mutation where possible; preserve branch/PR/issues for safe retry.
  • Definition of done: DOD-1 local acceptance; G01-FLOW additionally needs T17 integration evidence. Do not claim publication/activation based on planning alone.

P01-T15 β€” Issue and milestone reconciliation

  • ID / priority / status: P01-T15 / MUST / NOT STARTED.
  • Goal: Create/reuse the current phase task records from canonical roadmap.
  • Why: Avoid manual bookkeeping and duplicate issue creation.
  • Inputs: DELIVERY_WORKFLOW issue schema; TASK_ISSUE template; P01-T14.
  • Files/areas expected: scripts issue/milestone adapter; phase ledger; repository issue template if useful.
  • Dependencies: P01-T14; original foundation evidence; current session publication scope.
  • Tests first: Paginated duplicate/open/closed task markers, human notes preserved, retry after API failure, dry-run no writes.
  • Implementation outline: Read active phase only; match stable markers; synchronize owned fields/labels; link milestone/PR; keep locally completed tasks open until merge.
  • Acceptance criteria: Idempotent preview lists exact real/missing records; cannot close completed-looking but unmerged tasks.
  • Validation commands: Run reconciliation fixtures with fake API; review upcoming phase preview before authorized publication. Record the exact created executable commands and outcomes in the task evidence.
  • Risks: Duplicate spam, overwriting discussion or recreating historical P01 issues.
  • Rollback/Recovery: Stop remote reconciliation; keep IDs/result ledger and retry only missing mutations.
  • Definition of done: DOD-1 local acceptance; G01-FLOW additionally needs T17 integration evidence. Do not claim publication/activation based on planning alone.

P01-T16 β€” Wiki mirror with owned-page manifest

  • ID / priority / status: P01-T16 / MUST / NOT STARTED.
  • Goal: Generate a navigable wiki snapshot from merged documentation.
  • Why: Keep public progress current without per-task manual rewriting.
  • Inputs: DELIVERY_WORKFLOW wiki rules; docs index; P01-T15.
  • Files/areas expected: scripts wiki exporter/publisher; generated-page manifest; fixture wiki repo.
  • Dependencies: P01-T15; original foundation evidence; current session publication scope.
  • Tests first: Nested README collision, rewritten links/anchors/assets, manual page preserved, edited managed page conflict, obsolete-owned-only deletion, identical snapshot no-op.
  • Implementation outline: Export allowlisted docs at explicit merged SHA; generate Home/sidebar; validate second remote/scope; publish only within authorized wiki scope.
  • Acceptance criteria: Offline preview complete with source SHA; no blanket Markdown deletion; no production/private content; failure leaves WIKI_PENDING.
  • Validation commands: Run exporter tests against temporary local Git/wiki repositories and link checks; inspect publish dry-run. Record the exact created executable commands and outcomes in the task evidence.
  • Risks: Losing hand-written wiki content or leaking private logs.
  • Rollback/Recovery: Keep prior wiki commit; stop on conflicts; retry docs sync without backend reruns.
  • Definition of done: DOD-1 local acceptance; G01-FLOW additionally needs T17 integration evidence. Do not claim publication/activation based on planning alone.

P01-T17 β€” Activate CI cadence and protected phase integration

  • ID / priority / status: P01-T17 / MUST / NOT STARTED.
  • Goal: Safely switch actual workflows/protection and prove end-to-end delivery.
  • Why: Make the new plan operational without a protection gap.
  • Inputs: CI_PLAN transition; P01-T13…T16 evidence.
  • Files/areas expected: .github/workflows; configured branch protection; delivery docs/state; controlled PR evidence.
  • Dependencies: P01-T16; original foundation evidence; current session publication scope.
  • Tests first: Draft and docs-only PR run named quick; absent/old/changed-head check blocks; full jobs only selected release/tag; current protections remain until replacement verified.
  • Implementation outline: Introduce quick, observe required result, update protections/triggers in reviewed order, exercise authorized phase PR; verify issue closure and wiki publication/pending record.
  • Acceptance criteria: G01-FLOW complete only with actual observed checks/protection; origin confirmed; missing permissions or required checks remain BLOCKED.
  • Validation commands: Validate workflow config and controller harness; inspect one controlled authorized PR check/head/base/merge and actual branch protection; review wiki result independently. Record the exact created executable commands and outcomes in the task evidence.
  • Risks: Required check disappears during transition; plan falsely labelled deployed.
  • Rollback/Recovery: Keep/restore prior checks until replacement works; never bypass main protection or publish untested release.
  • Definition of done: DOD-1 local acceptance; G01-FLOW additionally needs T17 integration evidence. Do not claim publication/activation based on planning alone.

P02 β€” Official catalog and ANP ingestion

Priority: MUST. Entry: G01 + G01-FLOW.

Exit gate: G02: canonical station identity, precise units/CNPJ, idempotent revisioned import, quarantine/reporting, permitted geolocation path and public official reads validated; no Android modifications.

P02-T01 β€” Shared ANP fixtures

  • ID / priority / status: P02-T01 / MUST / NOT STARTED.
  • Goal: Capture versioned source normalization cases.
  • Why: Prevent parser divergence.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; CURRENT_STATE_AUDIT A03-A07.
  • Files/areas expected: contracts/testdata/anp; backend/testdata (area list, not a literal combined path).
  • Dependencies: G01 + G01-FLOW; all earlier phase gates.
  • Tests first: Verify sample hashes and expected legacy-versus-target outputs.
  • Implementation outline: Create manifest and cases including labels, precision, unit, header shifts and alphanumeric CNPJ.
  • Acceptance criteria: Each case has provenance and intentional compatibility classification.
  • Validation commands: Validate fixture JSON/schema and Go fixture-loader tests. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Copying production personal data or encoding a wrong assumption.
  • Rollback/Recovery: Correct an unpublished fixture with rationale; version already-consumed cases.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T02 β€” Price, product, condition and CNPJ values

  • ID / priority / status: P02-T02 / MUST / NOT STARTED.
  • Goal: Implement exact validated backend value objects.
  • Why: Centralize stable import/community invariants.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; DOMAIN_MODEL B-BR-002; shared fixtures.
  • Files/areas expected: backend/internal/modules/directory/domain; backend/internal/modules/community/domain; minimal shared values (area list, not a literal combined path).
  • Dependencies: P02-T01; all earlier phase gates.
  • Tests first: GIVEN valid/invalid numeric/alphanumeric CNPJ, units and integer price THEN expected value/error.
  • Implementation outline: Implement separate small values; no I/O or float money; split into separate PRs if needed.
  • Acceptance criteria: All edge fixtures pass; source letters/leading zeroes preserved.
  • Validation commands: cd backend && go test ./internal/modules/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Overbroad shared kernel or semantic drift.
  • Rollback/Recovery: Revert value implementation before schema depends on it.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T03 β€” Canonical station repository

  • ID / priority / status: P02-T03 / MUST / NOT STARTED.
  • Goal: Persist station identifiers and location revisions.
  • Why: Avoid duplicate station identity across sources.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; DATA_MODEL Directory; B-BR-014.
  • Files/areas expected: backend/internal/modules/directory; backend/db/migrations; backend/db/queries/directory (area list, not a literal combined path).
  • Dependencies: P02-T02; all earlier phase gates.
  • Tests first: Concurrent same CNPJ produces one station; aliases and missing location cases.
  • Implementation outline: Add owned schema/repository and explicit resolver interface.
  • Acceptance criteria: Stable UUID, constraints and indexes pass real DB tests.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/directory/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Merging unrelated businesses by address.
  • Rollback/Recovery: Append correction/alias review; never delete linked observation history.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T04 β€” Bounded ANP parser

  • ID / priority / status: P02-T04 / MUST / NOT STARTED.
  • Goal: Parse summary/station workbook streams safely.
  • Why: Convert actual source files with explainable rejection.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; ANP_INGESTION; D06.
  • Files/areas expected: backend/internal/modules/official/adapters/anp (area list, not a literal combined path).
  • Dependencies: P02-T03; all earlier phase gates.
  • Tests first: Header shift, unknown label, exact decimal, malformed XML/ZIP and size-limit failures.
  • Implementation outline: Resolve parser library decision then implement discovery-independent parsing.
  • Acceptance criteria: Fixtures pass; memory/input caps measured; no formula execution.
  • Validation commands: cd backend && go test ./internal/modules/official/adapters/anp/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Layout drift or decompression resource exhaustion.
  • Rollback/Recovery: Keep last published revision; quarantine inputs and roll back parser.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T05 β€” ANP source discovery and download

  • ID / priority / status: P02-T05 / MUST / NOT STARTED.
  • Goal: Download only approved official sources with checksum.
  • Why: Avoid SSRF and unverifiable provenance.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; ANP_INGESTION.
  • Files/areas expected: backend/internal/modules/official/adapters/source (area list, not a literal combined path).
  • Dependencies: P02-T04; all earlier phase gates.
  • Tests first: Redirect to disallowed/private host rejected; checksum/timeout/cancel tests.
  • Implementation outline: Allowlist hosts/paths, conditional fetch, limits and temporary-file cleanup.
  • Acceptance criteria: No arbitrary URL fetch; fixtures cover discovery changes.
  • Validation commands: cd backend && go test ./internal/modules/official/adapters/source/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Redirect bypass or stale catalog.
  • Rollback/Recovery: Disable import scheduling and retain last known source revision.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T06 β€” Revisioned publication

  • ID / priority / status: P02-T06 / MUST / NOT STARTED.
  • Goal: Stage and publish imports atomically.
  • Why: Correct ANP revisions without overwriting history.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; B-BR-013; DATA_MODEL Official.
  • Files/areas expected: backend/internal/modules/official; backend/db/migrations; backend/db/queries/official (area list, not a literal combined path).
  • Dependencies: P02-T05; all earlier phase gates.
  • Tests first: Same bytes no-op, corrected bytes new revision, partial batch invisible, quarantine threshold.
  • Implementation outline: Persist runs/rows/revisions; validate then switch publication pointer.
  • Acceptance criteria: Previous revision stays readable and retry is safe.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/official/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Publishing partial/empty source or duplicate revisions.
  • Rollback/Recovery: Reset active pointer via audited application action; preserve both revisions.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T07 β€” Catalog geolocation adapter

  • ID / priority / status: P02-T07 / MUST / NOT STARTED.
  • Goal: Store verified station coordinates with provenance.
  • Why: Enable nearby queries without live geocoder calls.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; ANP_INGESTION; D05.
  • Files/areas expected: backend/internal/modules/directory/adapters/geocoder (area list, not a literal combined path).
  • Dependencies: P02-T06; all earlier phase gates.
  • Tests first: Cache/quota/timeout/ambiguous result and missing-coordinate fixtures.
  • Implementation outline: Select permitted provider for pilot, add global throttle/cache and reviewed location changes.
  • Acceptance criteria: Unknown/centroid not treated as verified station; attribution recorded.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/directory/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Provider policy breach or false coordinates.
  • Rollback/Recovery: Disable provider and retain last reviewed location revision.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P02-T08 β€” Station and official price read API

  • ID / priority / status: P02-T08 / MUST / NOT STARTED.
  • Goal: Expose source-labelled directory and official history.
  • Why: Make the catalog usable before community write path.
  • Inputs: docs/backend/ANP_INGESTION.md, docs/backend/DATA_MODEL.md; API_PLAN public reads.
  • Files/areas expected: contracts/openapi; backend/internal/modules/directory; backend/internal/modules/official (area list, not a literal combined path).
  • Dependencies: P02-T07; all earlier phase gates.
  • Tests first: Contract/error/pagination/geo bounds and query plan tests.
  • Implementation outline: Implement owned read adapters and explicit cache/no-store policies.
  • Acceptance criteria: Station/nearby/history responses validate; missing location honest.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/directory/... ./internal/modules/official/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Precise query coordinates in logs/cache or expensive spatial scans.
  • Rollback/Recovery: Rollback handler version; keep data and previous contract semantics.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03 β€” Anonymous identity and durable work

Priority: MUST. Entry: G02.

Exit gate: G03: verified registration/rotation/signatures, atomic replay defense, durable idempotency/quotas and lease-based queue, with concurrency and crash tests.

P03-T01 β€” Authentication byte-level vectors

  • ID / priority / status: P03-T01 / MUST / NOT STARTED.
  • Goal: Freeze interoperable signature profile.
  • Why: Avoid unsafe custom serialization.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; API_PLAN; ADR-007.
  • Files/areas expected: contracts/testdata/identity; docs/security/identity-profile.md (area list, not a literal combined path).
  • Dependencies: G02; all earlier phase gates.
  • Tests first: RFC vector verification and changed method/path/body/authority rejection.
  • Implementation outline: Specify covered components, P-256 encoding, challenge binding and trusted proxy behavior.
  • Acceptance criteria: Independent verifier agrees; no ambiguous header acceptance.
  • Validation commands: Run documented Go plus independent standard-library protocol-vector tests. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Signature format/proxy mismatch.
  • Rollback/Recovery: Revise unpublished profile before endpoint implementation.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T02 β€” Contributor registration

  • ID / priority / status: P03-T02 / MUST / NOT STARTED.
  • Goal: Register key ownership without personal-account fields.
  • Why: Allow free contribution without email.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; BUC-002; B-BR-004.
  • Files/areas expected: backend/internal/modules/identity; backend/db/migrations; contracts/openapi (area list, not a literal combined path).
  • Dependencies: P03-T01; all earlier phase gates.
  • Tests first: Bad key, proof failure, duplicate fingerprint and registration retry cases.
  • Implementation outline: Persist candidate challenge and key proof atomically; public JWK only.
  • Acceptance criteria: Same key cannot acquire another contributor; proof required.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/identity/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Unauthenticated registration flood.
  • Rollback/Recovery: Disable registration temporarily; preserve existing valid identities.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T03 β€” Signed requests and replay defense

  • ID / priority / status: P03-T03 / MUST / NOT STARTED.
  • Goal: Verify required proof and consume nonce atomically.
  • Why: Protect all owner reads/writes.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; identity-profile; B-BR-004.
  • Files/areas expected: backend/internal/modules/identity; HTTP auth adapter (area list, not a literal combined path).
  • Dependencies: P03-T02; all earlier phase gates.
  • Tests first: Concurrent same nonce accepts once; skew, expiry, revoked key, signed-read replay.
  • Implementation outline: Use DB challenge state and strict request profile; no RAM-only authority.
  • Acceptance criteria: Changed components rejected; original contributor derived server-side.
  • Validation commands: cd backend && go test -race -tags=integration ./internal/modules/identity/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Replay window or transaction race.
  • Rollback/Recovery: Pause writes; roll back binary and expire pending challenges.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T04 β€” Operation idempotency

  • ID / priority / status: P03-T04 / MUST / NOT STARTED.
  • Goal: Persist request outcome and permanent command identity.
  • Why: Make mobile retries safe.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; B-BR-005; API_PLAN.
  • Files/areas expected: backend/internal/modules/identity/application; persistence adapter (area list, not a literal combined path).
  • Dependencies: P03-T03; all earlier phase gates.
  • Tests first: Same key/body returns original; changed body conflicts; lost-response retry.
  • Implementation outline: Transaction-aware idempotency repository; safe stored responses; seven-day expiry.
  • Acceptance criteria: No double execution; new nonce allowed for same command.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/identity/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Conflating replay and retry or retaining sensitive body.
  • Rollback/Recovery: Keep durable keys; correct handler via forward fix.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T05 β€” Registration and write quotas

  • ID / priority / status: P03-T05 / MUST / NOT STARTED.
  • Goal: Enforce shared contributor/IP operation limits.
  • Why: Bound abuse/cost across API replicas.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; B-BR-015; SECURITY_PRIVACY.
  • Files/areas expected: backend/internal/modules/identity; edge config plan (area list, not a literal combined path).
  • Dependencies: P03-T04; all earlier phase gates.
  • Tests first: Concurrent quota boundary, NAT throttling response and expiry cleanup.
  • Implementation outline: Atomic DB counters, rotating IP digest, 429/Retry-After; edge additive limits.
  • Acceptance criteria: No successful operations exceed configured transactional quota.
  • Validation commands: cd backend && go test -race -tags=integration ./internal/modules/identity/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: IP-only bans or memory-only counters.
  • Rollback/Recovery: Adjust versioned quota config with audit; preserve abuse evidence within retention.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T06 β€” Key rotation and revocation

  • ID / priority / status: P03-T06 / MUST / NOT STARTED.
  • Goal: Rotate with old/new proofs and preserve contributor.
  • Why: Avoid losing or stealing reputation.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; BUC-002; API_PLAN.
  • Files/areas expected: backend/internal/modules/identity; contracts/openapi (area list, not a literal combined path).
  • Dependencies: P03-T05; all earlier phase gates.
  • Tests first: Old/new proof failure, concurrent rotation, old key revoked, new key works.
  • Implementation outline: Atomic key replacement, no anonymous lost-key recovery promise.
  • Acceptance criteria: Rotation keeps contributor and disallows old signed writes.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/identity/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Lockout or unauthorized reputation takeover.
  • Rollback/Recovery: Restricted incident procedure; never restore compromised key automatically.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T07 β€” PostgreSQL job queue

  • ID / priority / status: P03-T07 / MUST / NOT STARTED.
  • Goal: Claim durable work with leases and fencing.
  • Why: Support validation/import/retention without broker.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; TARGET_ARCHITECTURE jobs.
  • Files/areas expected: backend/internal/platform/jobs; backend/db/migrations (area list, not a literal combined path).
  • Dependencies: P03-T06; all earlier phase gates.
  • Tests first: Two workers, lease expiry, stale ack, crash after effect, poison job cases.
  • Implementation outline: Transactional enqueue; SKIP LOCKED claim; capped retries; dead-job replay command.
  • Acceptance criteria: One durable business effect per dedupe/version despite repeated delivery.
  • Validation commands: cd backend && go test -race -tags=integration ./internal/platform/jobs/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Stale worker overwrites or infinite retry.
  • Rollback/Recovery: Pause job type, fix handler, replay DEAD jobs with audited reason.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P03-T08 β€” Worker dispatch and recurring schedules

  • ID / priority / status: P03-T08 / MUST / NOT STARTED.
  • Goal: Schedule official imports and connect durable handlers.
  • Why: Turn the queue into operational background processing.
  • Inputs: docs/backend/API_PLAN.md, docs/security/SECURITY_PRIVACY.md; ANP_INGESTION; TARGET_ARCHITECTURE jobs.
  • Files/areas expected: backend/cmd/worker; backend/internal/platform/jobs; official/directory application adapters (area list, not a literal combined path).
  • Dependencies: P03-T07; all earlier phase gates.
  • Tests first: Restart duplicate scheduling, one due job per period, cancellation and slow provider cases.
  • Implementation outline: Register explicit typed handlers; persist schedule dedupe keys; enqueue daily discovery and bounded permitted geocoding; later tasks add their own handlers.
  • Acceptance criteria: Worker process executes imports after restart without duplicate publications; unsupported payload versions fail safely.
  • Validation commands: cd backend && go test -race -tags=integration ./internal/platform/jobs/... ./internal/modules/official/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: In-memory-only schedules or duplicate live imports.
  • Rollback/Recovery: Pause affected schedule; replay durable jobs with dedupe and preserve published revisions.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P04 β€” Observation history and lifecycle

Priority: MUST. Entry: G03.

Exit gate: G04: durable immutable observations and decisions, ownership/idempotency, safe status API, validation orchestration; no current-price claim at receipt.

P04-T01 β€” Observation aggregate

  • ID / priority / status: P04-T01 / MUST / NOT STARTED.
  • Goal: Create an immutable observation under domain invariants.
  • Why: Capture facts without overwriting current price.
  • Inputs: docs/backend/DOMAIN_MODEL.md, docs/backend/COMMUNITY_PRICING_SPEC.md; B-BR-001…005; BUC-003.
  • Files/areas expected: backend/internal/modules/community/domain (area list, not a literal combined path).
  • Dependencies: G03; all earlier phase gates.
  • Tests first: Invalid amount/unit/condition/supersedes and server-time invariants.
  • Implementation outline: Implement aggregate construction and PriceObserved event; injected clock/IDs.
  • Acceptance criteria: No client-controlled trust/contributor/server timestamp.
  • Validation commands: cd backend && go test ./internal/modules/community/domain/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Mutable fact fields or accidental precision loss.
  • Rollback/Recovery: Revert unshipped aggregate; corrections later append new facts.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P04-T02 β€” Validation state machine

  • ID / priority / status: P04-T02 / MUST / NOT STARTED.
  • Goal: Control admissibility through domain transitions.
  • Why: Keep state changes out of HTTP handlers.
  • Inputs: docs/backend/DOMAIN_MODEL.md, docs/backend/COMMUNITY_PRICING_SPEC.md; DOMAIN_MODEL state machine.
  • Files/areas expected: backend/internal/modules/community/domain (area list, not a literal combined path).
  • Dependencies: P04-T01; all earlier phase gates.
  • Tests first: Enumerate valid/invalid transitions, terminal rejection and moderation path.
  • Implementation outline: Separate immutable decision events from state projection and job processing.
  • Acceptance criteria: Every transition has actor/reason/event tests.
  • Validation commands: cd backend && go test ./internal/modules/community/domain/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Conflating expired/confidence/dispute with validation state.
  • Rollback/Recovery: Append correcting decision under policy; never edit old decision.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P04-T03 β€” Observation persistence

  • ID / priority / status: P04-T03 / MUST / NOT STARTED.
  • Goal: Persist facts, decisions, idempotency and job atomically.
  • Why: Prevent accepted but unprocessed writes.
  • Inputs: docs/backend/DOMAIN_MODEL.md, docs/backend/COMMUNITY_PRICING_SPEC.md; DATA_MODEL Community.
  • Files/areas expected: backend/internal/modules/community/adapters; backend/db/migrations; queries/community (area list, not a literal combined path).
  • Dependencies: P04-T02; all earlier phase gates.
  • Tests first: Rollback on enqueue failure, concurrent submission ID, disallowed destructive update.
  • Implementation outline: Implement repository/transaction and indexes with least-privilege roles.
  • Acceptance criteria: Retry yields same observation; history protected.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/community/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Partial commit or duplicate history.
  • Rollback/Recovery: Forward migration fix; retain original facts and dedupe keys.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P04-T04 β€” Observation submit and owner status

  • ID / priority / status: P04-T04 / MUST / NOT STARTED.
  • Goal: Expose contracted write/status/history endpoints.
  • Why: Give mobile retries a safe acknowledgment.
  • Inputs: docs/backend/DOMAIN_MODEL.md, docs/backend/COMMUNITY_PRICING_SPEC.md; API_PLAN; BUC-003.
  • Files/areas expected: contracts/openapi; backend/internal/modules/community HTTP/application (area list, not a literal combined path).
  • Dependencies: P04-T03; all earlier phase gates.
  • Tests first: Authz/IDOR, malformed field, no-store, 201 RECEIVED and retry contract.
  • Implementation outline: Map DTO through use case to repository; owner-only status pagination.
  • Acceptance criteria: OpenAPI responses match; no claim of publication before validation.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/community/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Publishing raw evidence/GPS or accepting client contributor ID.
  • Rollback/Recovery: Rollback routes while retaining accepted jobs/history.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P04-T05 β€” Validation orchestration

  • ID / priority / status: P04-T05 / MUST / NOT STARTED.
  • Goal: Process received observations through owned ports.
  • Why: Prepare honest eligibility before evidence/consensus.
  • Inputs: docs/backend/DOMAIN_MODEL.md, docs/backend/COMMUNITY_PRICING_SPEC.md; BUC-003; B-BR-010/014.
  • Files/areas expected: backend/internal/modules/community/application; worker wiring (area list, not a literal combined path).
  • Dependencies: P04-T04; all earlier phase gates.
  • Tests first: Missing station/evidence pending, unknown location, transient failure and permanent reject.
  • Implementation outline: Use read-only station/trust/evidence ports; persist transition plus downstream intent.
  • Acceptance criteria: Metadata-only path explicit; media-required path waits up to policy deadline.
  • Validation commands: cd backend && go test ./internal/modules/community/application/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Accidentally treating unavailable signals as verified.
  • Rollback/Recovery: Pause validator, replay after fix; preserve received facts.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P05 β€” Private evidence

Priority: MUST. Entry: G04.

Exit gate: G05: direct upload with bounded quotas, frozen server-validated evidence, ownership, retry/orphan/retention behavior proven with real storage staging.

P05-T01 β€” Upload session domain

  • ID / priority / status: P05-T01 / MUST / NOT STARTED.
  • Goal: Reserve owned upload sessions under limits.
  • Why: Reject expensive invalid intent early.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/API_PLAN.md; B-BR-010/015; BUC-004.
  • Files/areas expected: backend/internal/modules/evidence/domain; application (area list, not a literal combined path).
  • Dependencies: G04; all earlier phase gates.
  • Tests first: Quota, MIME, size, ownership and expiry cases.
  • Implementation outline: Implement session state and reservation; no client object key.
  • Acceptance criteria: Only allowed intent reaches object-store adapter.
  • Validation commands: cd backend && go test ./internal/modules/evidence/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: State permits quota bypass.
  • Rollback/Recovery: Expire unprocessed sessions and release unused reservation safely.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P05-T02 β€” S3 adapter and presigned upload

  • ID / priority / status: P05-T02 / MUST / NOT STARTED.
  • Goal: Issue short direct PUT authorization.
  • Why: Avoid proxying photos through API handlers.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/API_PLAN.md; ADR-010; API_PLAN.
  • Files/areas expected: backend/internal/modules/evidence/adapters/storage; contracts/openapi (area list, not a literal combined path).
  • Dependencies: P05-T01; all earlier phase gates.
  • Tests first: Private ACL, signed headers, expired URL, wrong owner/object key.
  • Implementation outline: Minimal S3-compatible adapter; server keys; least-privilege credentials.
  • Acceptance criteria: Client can upload only its quarantine object; bucket stays private.
  • Validation commands: Run storage integration suite with emulator then isolated R2 staging bucket. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Assuming PUT enforces content size or one-time use.
  • Rollback/Recovery: Revoke storage credential if leaked; expire sessions; preserve validated final objects.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P05-T03 β€” Safe image verification

  • ID / priority / status: P05-T03 / MUST / NOT STARTED.
  • Goal: Validate a bounded snapshot and sanitize media.
  • Why: Stop metadata spoofing and upload overwrite races.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/API_PLAN.md; SECURITY_PRIVACY evidence protocol.
  • Files/areas expected: backend/internal/modules/evidence/application; media adapter; testdata (area list, not a literal combined path).
  • Dependencies: P05-T02; all earlier phase gates.
  • Tests first: Oversize, malformed/JPEG bomb, EXIF, swapped object and polyglot fixtures.
  • Implementation outline: Bounded download/decode; server hash; re-encode to immutable final key.
  • Acceptance criteria: Only verified snapshot becomes READY; EXIF stripped.
  • Validation commands: cd backend && go test ./internal/modules/evidence/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Decoder resource exhaustion or TOCTOU bug.
  • Rollback/Recovery: Pause validation, quarantine affected objects, forward fix and replay.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P05-T04 β€” Completion and observation binding

  • ID / priority / status: P05-T04 / MUST / NOT STARTED.
  • Goal: Finalize asynchronously and bind owner evidence once.
  • Why: Handle mobile duplicate finalize and lost responses.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/API_PLAN.md; BUC-004; API_PLAN.
  • Files/areas expected: backend/internal/modules/evidence; community evidence port; queries (area list, not a literal combined path).
  • Dependencies: P05-T03; all earlier phase gates.
  • Tests first: Duplicate complete, upload success/DB failure, reused evidence, owner mismatch.
  • Implementation outline: Persist intent/job; READY binding transaction; safe status endpoint.
  • Acceptance criteria: No publicly downloadable evidence; no duplicate binding.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/evidence/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Reference to mutable/deleted object.
  • Rollback/Recovery: Reconcile session/object state and retry; do not fabricate readiness.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P05-T05 β€” Media cleanup and hash signals

  • ID / priority / status: P05-T05 / MUST / NOT STARTED.
  • Goal: Expire originals/orphans and retain bounded duplicate signals.
  • Why: Control storage cost and privacy.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/API_PLAN.md; B-BR-016; SECURITY_PRIVACY.
  • Files/areas expected: backend/internal/modules/evidence; retention jobs (area list, not a literal combined path).
  • Dependencies: P05-T04; all earlier phase gates.
  • Tests first: Active lease not deleted, true orphan deleted, repeated cleanup safe, duplicate hash case.
  • Implementation outline: Original cap 24 h, sanitized 14 days, case extension ≀30 days, hashes 90 days.
  • Acceptance criteria: Lifecycle matches inventory and cleanup observable.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/evidence/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Deleting in-flight object or indefinite retention.
  • Rollback/Recovery: Pause sweeper, fix eligibility; missing evidence remains marked unavailable.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P06 β€” Consensus and contributor trust

Priority: MUST. Entry: G05.

Exit gate: G06: deterministic weighted projection with independent votes, conditions, expiry, disputes and conservative trust; golden/race tests prove invariants and payment isolation.

P06-T01 β€” Derived validation signals

  • ID / priority / status: P06-T01 / MUST / NOT STARTED.
  • Goal: Derive proximity, recency and risk without long-lived GPS.
  • Why: Make confidence inputs explainable and minimized.
  • Inputs: docs/backend/COMMUNITY_PRICING_SPEC.md, docs/backend/DATA_MODEL.md; B-BR-011/014; COMMUNITY_PRICING_SPEC.
  • Files/areas expected: backend/internal/modules/community/application; private payload store (area list, not a literal combined path).
  • Dependencies: G05; all earlier phase gates.
  • Tests first: Missing/poor GPS, unknown station point, old capture, duplicate image, regional deviation.
  • Implementation outline: Persist only derived bands/reason codes; purge exact data after derivation.
  • Acceptance criteria: No single weak signal certifies truth; suspicious facts enter review.
  • Validation commands: cd backend && go test ./internal/modules/community/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: False certainty or retention leak.
  • Rollback/Recovery: Version signal policy; re-evaluate permitted facts without resurrecting deleted GPS.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P06-T02 β€” Confirmation and dispute commands

  • ID / priority / status: P06-T02 / MUST / NOT STARTED.
  • Goal: Record unique independent support and reports.
  • Why: Let contributors corroborate or contest safely.
  • Inputs: docs/backend/COMMUNITY_PRICING_SPEC.md, docs/backend/DATA_MODEL.md; B-BR-006; BUC-005.
  • Files/areas expected: backend/internal/modules/community; contracts/openapi; migrations (area list, not a literal combined path).
  • Dependencies: P06-T01; all earlier phase gates.
  • Tests first: Self-confirmation, duplicates, concurrency, repeated dispute, wrong target state.
  • Implementation outline: Unique votes/reports with transactionally enqueued recalculation.
  • Acceptance criteria: One contributor cannot amplify support; reports do not automatically erase prices.
  • Validation commands: cd backend && go test -race -tags=integration ./internal/modules/community/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Coordinated reports deny valid data.
  • Rollback/Recovery: Moderate cases and recompute; retain reports/audit within retention.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P06-T03 β€” Conservative trust ledger

  • ID / priority / status: P06-T03 / MUST / NOT STARTED.
  • Goal: Promote reliability only from independent reviewed outcomes.
  • Why: Avoid self-reinforcing Sybil reputation.
  • Inputs: docs/backend/COMMUNITY_PRICING_SPEC.md, docs/backend/DATA_MODEL.md; trust-v1; B-BR-009.
  • Files/areas expected: backend/internal/modules/trust; migrations; queries/trust (area list, not a literal combined path).
  • Dependencies: P06-T02; all earlier phase gates.
  • Tests first: Age/day/outcome boundaries, blocked/reversed state, payment invariance.
  • Implementation outline: Append trust decisions and expose read port; event to recalculate affected keys.
  • Acceptance criteria: No raw volume/paid plan grants trust.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/trust/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Circular trust promotion or inherited purchase influence.
  • Rollback/Recovery: Publish new trust decision/policy and recompute.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P06-T04 β€” Consensus pure algorithm

  • ID / priority / status: P06-T04 / MUST / NOT STARTED.
  • Goal: Implement deterministic consensus-v1 golden cases.
  • Why: Compute explainable price instead of last-write-wins.
  • Inputs: docs/backend/COMMUNITY_PRICING_SPEC.md, docs/backend/DATA_MODEL.md; COMMUNITY_PRICING_SPEC; B-BR-007/008.
  • Files/areas expected: backend/internal/modules/community/domain; contracts/testdata/consensus (area list, not a literal combined path).
  • Dependencies: P06-T03; all earlier phase gates.
  • Tests first: All required golden cases plus permutation/ties/expiry/conflict and no paid weight.
  • Implementation outline: Exact amount groups, one vote/contributor, recency/trust weights and confidence gates.
  • Acceptance criteria: Same facts/time/version always produce same output.
  • Validation commands: cd backend && go test ./internal/modules/community/domain/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: False-high confidence or underspecified ties.
  • Rollback/Recovery: Switch back to prior version and rebuild restricted affected keys.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P06-T05 β€” Projection and read publication

  • ID / priority / status: P06-T05 / MUST / NOT STARTED.
  • Goal: Persist current prices with race-safe recomputation and expiry.
  • Why: Keep reads cheap and never current past expiry.
  • Inputs: docs/backend/COMMUNITY_PRICING_SPEC.md, docs/backend/DATA_MODEL.md; DATA_MODEL projection; API_PLAN.
  • Files/areas expected: backend/internal/modules/community; jobs; price response OpenAPI (area list, not a literal combined path).
  • Dependencies: P06-T04; all earlier phase gates.
  • Tests first: Concurrent jobs, stale worker, timed decay, worker down at expiry, mixed sources.
  • Implementation outline: Lock price key before load; version output; schedule boundary recompute; query-time expiry.
  • Acceptance criteria: Indexed GET returns source-separated response without history replay.
  • Validation commands: cd backend && go test -race -tags=integration ./internal/modules/community/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Old worker wins or stale CDN price survives expiry.
  • Rollback/Recovery: Invalidate cache and rebuild projection from eligible retained facts.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P07 β€” Moderation and privacy operations

Priority: MUST. Entry: G06.

Exit gate: G07: restricted audited operations, appeal/abuse handling, export/erasure and retention jobs with restore-safe deletion ledger.

P07-T01 β€” Moderation case queue

  • ID / priority / status: P07-T01 / MUST / NOT STARTED.
  • Goal: Create bounded actionable cases from reports/signals.
  • Why: Make abuse review feasible without a dashboard.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/DOMAIN_MODEL.md; B-BR-012; BUC-006.
  • Files/areas expected: backend/internal/modules/moderation; migrations (area list, not a literal combined path).
  • Dependencies: G06; all earlier phase gates.
  • Tests first: Duplicate case, priority ordering and safe evidence-reference tests.
  • Implementation outline: Owned case repository and cursor query with minimal sensitive fields.
  • Acceptance criteria: Operators can locate pending case and reasons.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/moderation/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Unbounded noisy queue or copied private payload.
  • Rollback/Recovery: Tune case admission; retain original reports and processing state.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P07-T02 β€” Restricted operator commands

  • ID / priority / status: P07-T02 / MUST / NOT STARTED.
  • Goal: Apply audited invalidation, blocking and reviewed overrides.
  • Why: Control privileged changes with accountable recovery.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/DOMAIN_MODEL.md; BUC-006; SECURITY_PRIVACY.
  • Files/areas expected: backend/cmd/ops; moderation application; access runbook (area list, not a literal combined path).
  • Dependencies: P07-T01; all earlier phase gates.
  • Tests first: Unauthorized operator denied; missing reason rejected; action/event/job atomic.
  • Implementation outline: CLI over restricted operator access; audited evidence URL; appeal creates new decision/fact.
  • Acceptance criteria: No anonymous/public admin path; history cannot be edited.
  • Validation commands: cd backend && go test -tags=integration ./internal/modules/moderation/.... Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Privilege escalation or unaudited manual SQL.
  • Rollback/Recovery: Revoke operator access; audited reversal and projection rebuild.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P07-T03 β€” Contributor export

  • ID / priority / status: P07-T03 / MUST / NOT STARTED.
  • Goal: Export authenticated owner data with short-lived access.
  • Why: Support transparent data access.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/DOMAIN_MODEL.md; BUC-007; API_PLAN.
  • Files/areas expected: backend/internal/modules/identity; privacy application; private export adapter (area list, not a literal combined path).
  • Dependencies: P07-T02; all earlier phase gates.
  • Tests first: Wrong owner, expired download, redacted unrelated contributors.
  • Implementation outline: Durable request/job; bounded archive; access after proof and private URL expiry.
  • Acceptance criteria: Export complete for inventory without leaking other contributors.
  • Validation commands: Run privacy integration/E2E export tests. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Export becomes a public long-lived data dump.
  • Rollback/Recovery: Expire/delete object and revoke exposed credential if applicable.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P07-T04 β€” Erasure and restore ledger

  • ID / priority / status: P07-T04 / MUST / NOT STARTED.
  • Goal: Remove personal data and reapply deletions after recovery.
  • Why: Resolve immutable history versus privacy rights.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/DOMAIN_MODEL.md; ADR-008; B-BR-016.
  • Files/areas expected: privacy application; cleanup jobs; deletion ledger; recovery runbook (area list, not a literal combined path).
  • Dependencies: P07-T03; all earlier phase gates.
  • Tests first: Erasure removes links/media/location; repeated request safe; backup restore reapplies deletion.
  • Implementation outline: Revoke writes, purge/unlink per reviewed policy, recompute affected prices; retain minimal bounded ledger.
  • Acceptance criteria: No restored erased data served before replay; receipt auditable.
  • Validation commands: Run privacy integration tests and isolated backup-restore deletion test. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Retaining identifying history under an immutability pretext.
  • Rollback/Recovery: Stop traffic after restore until ledger/retention checks pass.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P07-T05 β€” Retention scheduler and rights notice

  • ID / priority / status: P07-T05 / MUST / NOT STARTED.
  • Goal: Make every inventory period enforceable and visible.
  • Why: Prevent a paper-only privacy plan.
  • Inputs: docs/security/SECURITY_PRIVACY.md, docs/backend/DOMAIN_MODEL.md; SECURITY_PRIVACY inventory; BUC-007.
  • Files/areas expected: retention jobs; operator docs; draft backend privacy notice (area list, not a literal combined path).
  • Dependencies: P07-T04; all earlier phase gates.
  • Tests first: Clock boundary/pagination/batch retry tests for each retained data category.
  • Implementation outline: Schedule bounded purges; metrics on oldest overdue data; review lawful bases/contact process.
  • Acceptance criteria: Every collected field has purpose, retention, access and deletion behavior.
  • Validation commands: Run retention integration suite with accelerated fake clock. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Legal assumptions or unbounded holds.
  • Rollback/Recovery: Pause pilot collection for unresolved inventory item; fix cleanup then verify.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08 β€” Infrastructure and production hardening

Priority: MUST. Entry: G07.

Exit gate: G08: secured staging/prod topology and reproducible deployment, restricted roles, encrypted backups/restoration, monitoring, cache behavior, failure/load/security tests.

P08-T01 β€” Environment and network configuration

  • ID / priority / status: P08-T01 / MUST / NOT STARTED.
  • Goal: Prepare separate staging/production Compose and Caddy configs.
  • Why: Remove dev defaults from production path.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN; SECURITY_PRIVACY.
  • Files/areas expected: infra/compose.*.yml; infra/caddy; environment templates (area list, not a literal combined path).
  • Dependencies: G07; all earlier phase gates.
  • Tests first: Config validation rejects dev secrets, public DB/metrics and untrusted forwarded headers.
  • Implementation outline: Pin images, persistent volumes, resource limits, TLS/origin firewall and roles.
  • Acceptance criteria: Reviewable config with no purchased/provisioned resources unless execution authorized.
  • Validation commands: docker compose -f infra/compose.staging.yml config; run network/TLS smoke. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Accidentally exposing database or shared environment keys.
  • Rollback/Recovery: Revert network config; rotate exposed keys; never delete DB volume.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T02 β€” Deployment and rollback procedure

  • ID / priority / status: P08-T02 / MUST / NOT STARTED.
  • Goal: Deploy one versioned monolith release safely.
  • Why: Make migration/application ordering recoverable.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; DATA_MODEL migration policy; INFRASTRUCTURE_PLAN.
  • Files/areas expected: infra/scripts/deploy; release runbook; CI publish design (area list, not a literal combined path).
  • Dependencies: P08-T01; all earlier phase gates.
  • Tests first: Failed migration/readiness returns to previous compatible release.
  • Implementation outline: Backup precheck, migration lock, digest rollout and smoke/monitor steps.
  • Acceptance criteria: Staging rollback exercised; no destructive down migration required.
  • Validation commands: Run staging deployment/revert drill with synthetic data. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Mixed schema/binary versions.
  • Rollback/Recovery: Use tested prior binary plus forward schema fix; pause writes if needed.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T03 β€” Encrypted off-host backups

  • ID / priority / status: P08-T03 / MUST / NOT STARTED.
  • Goal: Create scheduled verifiable backup pipeline.
  • Why: Protect against VPS/volume loss.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN backup.
  • Files/areas expected: infra/scripts/backup; scheduler/runbook; credential scope (area list, not a literal combined path).
  • Dependencies: P08-T02; all earlier phase gates.
  • Tests first: Failed upload/expired credential/stale backup alarm and manifest verification.
  • Implementation outline: Daily dump with roles/extensions manifest and encryption; 7 daily/4 weekly copies.
  • Acceptance criteria: Off-host backup downloadable with independent recovery credentials.
  • Validation commands: Run backup to isolated destination and verify checksum manifest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Snapshot-only false assurance or keys stored on lost VPS.
  • Rollback/Recovery: Repair backup/key custody before accepting production writes.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T04 β€” Restore drill and deletion replay

  • ID / priority / status: P08-T04 / MUST / NOT STARTED.
  • Goal: Prove recovery in a new isolated environment.
  • Why: Validate RPO/RTO and privacy after restore.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; BUC-008; backup artifact.
  • Files/areas expected: infra/scripts/restore; docs/release-evidence (area list, not a literal combined path).
  • Dependencies: P08-T03; all earlier phase gates.
  • Tests first: Restore wrong/corrupt artifact rejected; deleted data stays removed.
  • Implementation outline: Restore full DB, verify counts/hashes, rebuild projections, replay ledger and check evidence references.
  • Acceptance criteria: Measured RPO≀24 h/RTO≀4 h or gate fails with revised accepted objective.
  • Validation commands: Run documented isolated restore drill and smoke suite. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Backup cannot restore or restores erased data.
  • Rollback/Recovery: Keep production closed; fix backup/replay and repeat drill.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T05 β€” Metrics, logs and operator alerts

  • ID / priority / status: P08-T05 / MUST / NOT STARTED.
  • Goal: Monitor actionable service and data-quality failures.
  • Why: Detect silent job/import/backup problems.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN budgets.
  • Files/areas expected: backend/internal/platform/telemetry; infra monitoring; runbooks (area list, not a literal combined path).
  • Dependencies: P08-T04; all earlier phase gates.
  • Tests first: Injected DB/job/backup failure triggers correct bounded alert; log redaction.
  • Implementation outline: Add metrics route privately, key dashboards/queries and tested notification route.
  • Acceptance criteria: No high-cardinality personal labels; owner knows response procedure.
  • Validation commands: Run failure injection and inspect metric/alert evidence. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Monitoring itself leaks personal data or floods operator.
  • Rollback/Recovery: Disable leaking field/label; adjust alerts without hiding real failures.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T06 β€” Public cache and proxy verification

  • ID / priority / status: P08-T06 / MUST / NOT STARTED.
  • Goal: Verify edge caching without identity/location leaks.
  • Why: Reduce read cost while preserving freshness.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; API_PLAN caching.
  • Files/areas expected: infra edge config documentation; staging API tests (area list, not a literal combined path).
  • Dependencies: P08-T05; all earlier phase gates.
  • Tests first: Authenticated/private/media/nearby never shared cached; expiry/ETag/purge tested.
  • Implementation outline: Allowlist public station GETs; canonical origin headers; bounded TTL.
  • Acceptance criteria: Cache behavior measured at edge; signed writes still verify through proxy.
  • Validation commands: Run staging cache/header/signature regression suite. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Shared cache disclosure or stale disputed prices.
  • Rollback/Recovery: Disable cache rule and purge; fall back to secured origin reads.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T07 β€” Load and failure campaign

  • ID / priority / status: P08-T07 / MUST / NOT STARTED.
  • Goal: Measure admission, reads, queues and recovery under faults.
  • Why: Choose pilot capacity from evidence.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; INFRASTRUCTURE_PLAN workload.
  • Files/areas expected: backend/testdata/load; infra/scripts/load; docs/release-evidence (area list, not a literal combined path).
  • Dependencies: P08-T06; all earlier phase gates.
  • Tests first: Seed deterministic data and assert workload/latency metrics before campaign.
  • Implementation outline: Run origin/cache scenarios, DB/R2/geocoder/worker faults and disk-pressure simulation.
  • Acceptance criteria: Budgets met or explicitly reduced/pending; no data loss or fake prices.
  • Validation commands: Run documented 30-minute acceptance load plus bounded fault suite. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Benchmarks on tiny data or misleading cache-only performance.
  • Rollback/Recovery: Throttle admissions/scale measured bottleneck; repeat failing scenario.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P08-T08 β€” Security and dependency release review

  • ID / priority / status: P08-T08 / MUST / NOT STARTED.
  • Goal: Close launch-blocking auth/privacy/storage vulnerabilities.
  • Why: Prevent unsafe pilot exposure.
  • Inputs: docs/backend/INFRASTRUCTURE_PLAN.md, docs/backend/TEST_STRATEGY.md; SECURITY_PRIVACY STRIDE; TEST_STRATEGY.
  • Files/areas expected: security regression tests; dependency inventory; release evidence (area list, not a literal combined path).
  • Dependencies: P08-T07; all earlier phase gates.
  • Tests first: Replay/IDOR/SSRF/oversize/role/secret cases; known-vulnerability scans.
  • Implementation outline: Review auth vectors, storage ACLs, least privilege and policy inventory; remediate focused findings.
  • Acceptance criteria: No unresolved critical/high findings; evidence linked.
  • Validation commands: cd backend && govulncheck ./...; run pinned secret/dependency/auth security gates. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: False confidence from scan-only review.
  • Rollback/Recovery: Block release until remediation verified; roll back insecure deployment.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P09 β€” Backend release gate before Android

Priority: MUST. Entry: G08.

Exit gate: G09: backend MVP and infrastructure fully exercised, release evidence accepted, no blocker in security/restore/catalog/identity/community/privacy; only then P10 can start.

P09-T01 β€” End-to-end backend release rehearsal

  • ID / priority / status: P09-T01 / MUST / NOT STARTED.
  • Goal: Exercise all MVP flows against deployed candidate.
  • Why: Prove modules work together beyond isolated tests.
  • Inputs: docs/product/PRODUCT_CONTRACT.md, docs/backend/TEST_STRATEGY.md; BUC-001…008; frozen OpenAPI.
  • Files/areas expected: backend/testdata/e2e; docs/release-evidence (area list, not a literal combined path).
  • Dependencies: G08; all earlier phase gates.
  • Tests first: Full register/upload/observe/confirm/dispute/moderate/export/erase flow plus denied paths.
  • Implementation outline: Select an immutable candidate after P01–P08 merges; run the full release matrix once on it with synthetic clients and inspect source separation and durable events/jobs.
  • Acceptance criteria: All critical flows pass deployed topology.
  • Validation commands: Run documented deployed E2E and full backend gate. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Happy-path-only evidence or accidental real personal-data use.
  • Rollback/Recovery: Rollback candidate and preserve synthetic failure evidence.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P09-T02 β€” Compatibility and documentation closure

  • ID / priority / status: P09-T02 / MUST / NOT STARTED.
  • Goal: Reconcile contract, baseline and runbooks.
  • Why: Avoid passing the gate with unresolved inherited assumptions.
  • Inputs: docs/product/PRODUCT_CONTRACT.md, docs/backend/TEST_STRATEGY.md; CURRENT_STATE_AUDIT; BASELINE_VALIDATION; MIGRATION_PLAN.
  • Files/areas expected: contracts; docs/planning; release evidence (area list, not a literal combined path).
  • Dependencies: P09-T01; all earlier phase gates.
  • Tests first: Review every A01-A13 resolution/defer rationale and fixture expectation.
  • Implementation outline: Use the same candidate matrix to include the existing Android regression baseline; freeze known legacy adapter deltas; verify links/runbooks without re-running unchanged aggregate evidence.
  • Acceptance criteria: No unspecified breaking semantic; baseline environment blockers resolved.
  • Validation commands: Run existing Android unit/lint/build gates and contract validation. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Treating planned Kotlin-Go harness as already passing.
  • Rollback/Recovery: Record blocked gate; no Android feature edits until prerequisites/evidence resolved.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P09-T03 β€” Backend readiness sign-off

  • ID / priority / status: P09-T03 / MUST / NOT STARTED.
  • Goal: Record the released bounded backend MVP and unblock P10.
  • Why: Enforce the user-requested ordering.
  • Inputs: docs/product/PRODUCT_CONTRACT.md, docs/backend/TEST_STRATEGY.md; G01…G08 evidence; D01…D12 decisions.
  • Files/areas expected: docs/release-evidence/G09.md; docs/planning/PROGRESS.md; ROADMAP.md status only (area list, not a literal combined path).
  • Dependencies: P09-T02; all earlier phase gates.
  • Tests first: Checklist rejects missing restore/security/privacy/load evidence or open launch blockers.
  • Implementation outline: Record commit/image/schema/policy/environment, operator readiness and rollback; mark gate only with proof.
  • Acceptance criteria: G09 COMPLETE with links and next P10-T01; otherwise remains BLOCKED.
  • Validation commands: Review all release evidence and smoke actual release endpoints. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Checkbox-only completion or scope creep into paid products.
  • Rollback/Recovery: Withdraw gate if material regression; keep Android integration unstarted.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10 β€” Android integration after G09

Priority: MUST. Entry: G09 COMPLETE required before ANY task in this phase.

Exit gate: G10: cross-language contracts, Room migration, identity, contribution/OCR, source/freshness UI, offline/outage tests and controlled pilot release; existing app preserved.

P10-T01 β€” Kotlin contract harness and compatibility adapters

  • ID / priority / status: P10-T01 / MUST / NOT STARTED.
  • Goal: Consume shared fixtures in the existing architecture.
  • Why: Resolve legacy fuel/CNPJ/precision differences explicitly.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; G09 evidence; ANP_INGESTION fixture manifest.
  • Files/areas expected: domain tests; data adapters/tests; contracts (area list, not a literal combined path).
  • Dependencies: G09 COMPLETE required before ANY task in this phase; all earlier phase gates.
  • Tests first: Legacy and target mapping fixtures, alpha CNPJ, exact decimal and unknown enums.
  • Implementation outline: Add Kotlin harness; bounded adapters only; no package moves.
  • Acceptance criteria: Go and Kotlin pass agreed fixtures; intended differences documented.
  • Validation commands: ./gradlew :domain:test :data:testDebugUnitTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Accidentally changing historical semantics.
  • Rollback/Recovery: Revert feature flag/adapters; retain original local data.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T02 β€” Community read ports and local cache

  • ID / priority / status: P10-T02 / MUST / NOT STARTED.
  • Goal: Add backend reads without removing ANP offline paths.
  • Why: Keep app useful on backend outage.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; API_PLAN; UC-004…009.
  • Files/areas expected: domain ports; application use cases; data HTTP/Room adapters (area list, not a literal combined path).
  • Dependencies: P10-T01; all earlier phase gates.
  • Tests first: Backend down, no cache, stale cache and schema-4 upgrade tests.
  • Implementation outline: Add source/version/expiry cache with explicit Room migration and feature flag.
  • Acceptance criteria: Local ANP screens work unchanged; migrations preserve vehicles/history.
  • Validation commands: ./gradlew :domain:test :application:test :data:testDebugUnitTest :data:connectedDebugAndroidTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Destructive local migration or mandatory network login.
  • Rollback/Recovery: Disable community reads; use compatible schema and prior local cache.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T03 β€” Device keys and anonymous protocol

  • ID / priority / status: P10-T03 / MUST / NOT STARTED.
  • Goal: Use Keystore and agreed proof on supported devices.
  • Why: Authenticate contribution without accounts.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; ADR-007; identity vectors.
  • Files/areas expected: data security adapter; application identity flow (area list, not a literal combined path).
  • Dependencies: P10-T02; all earlier phase gates.
  • Tests first: API26/current device key generation/signature interoperability, reinstall/rotation/lost key.
  • Implementation outline: Implement non-exportable P-256, challenges and rotation; honest loss warning.
  • Acceptance criteria: Real supported devices pass frozen protocol; no private key backup.
  • Validation commands: ./gradlew :data:testDebugUnitTest :data:connectedDebugAndroidTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Unproven secure hardware support or key export.
  • Rollback/Recovery: Disable new contribution flag and preserve usable anonymous identity.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T04 β€” Capture and local OCR

  • ID / priority / status: P10-T04 / MUST / NOT STARTED.
  • Goal: Capture/crop/compress and confirm extracted price.
  • Why: Reduce server cost and mistaken condition inference.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; COMMUNITY_PRICING_SPEC; new Android UC.
  • Files/areas expected: app capture UI; data CameraX/ML Kit adapter (area list, not a literal combined path).
  • Dependencies: P10-T03; all earlier phase gates.
  • Tests first: Permission denied, cancel, multiple prices/conditions, low OCR confidence.
  • Implementation outline: Record dependency rationale; local OCR candidates with human selection; no automatic lowest-price choice.
  • Acceptance criteria: No capture upload until contributor confirms content/condition.
  • Validation commands: ./gradlew :app:testDebugUnitTest :app:connectedDebugAndroidTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: OCR hallucinated condition or unauthorized photo collection.
  • Rollback/Recovery: Disable capture flag; retain metadata-only contribution.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T05 β€” Contribution outbox and direct media flow

  • ID / priority / status: P10-T05 / MUST / NOT STARTED.
  • Goal: Retry durable commands safely while offline.
  • Why: Handle real mobile disconnections.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; BUC-003/004; MIGRATION_PLAN outbox.
  • Files/areas expected: application contribution use cases; data Room/WorkManager/upload adapters (area list, not a literal combined path).
  • Dependencies: P10-T04; all earlier phase gates.
  • Tests first: Process death, duplicate send, old draft, object success/finalize failure.
  • Implementation outline: Stable command IDs, fresh nonce each retry, explicit queued/received/validated states.
  • Acceptance criteria: One observation per command; old photo not relabelled as fresh.
  • Validation commands: ./gradlew :application:test :data:testDebugUnitTest :data:connectedDebugAndroidTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Repeated submission or unbounded background upload.
  • Rollback/Recovery: Pause WorkManager contribution queue; do not delete accepted history.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T06 β€” Official and community price UI

  • ID / priority / status: P10-T06 / MUST / NOT STARTED.
  • Goal: Display source, condition, uncertainty and age separately.
  • Why: Make hybrid data understandable.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; PRODUCT_CONTRACT; API_PLAN.
  • Files/areas expected: app price/station UI; viewmodels; strings en/pt-BR (area list, not a literal combined path).
  • Dependencies: P10-T05; all earlier phase gates.
  • Tests first: UNKNOWN/DISPUTED/STALE, differing sources and APP qualifier display.
  • Implementation outline: Add distinct sections and accessible explanations; no silent source blending.
  • Acceptance criteria: Existing official browsing works; confidence not represented as guarantee.
  • Validation commands: ./gradlew :app:testDebugUnitTest :app:lintDebug :app:connectedDebugAndroidTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Misleading cheapest-price ranking or missing units.
  • Rollback/Recovery: Disable community panel via flag; keep ANP panel intact.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T07 β€” Confirm and dispute flows

  • ID / priority / status: P10-T07 / MUST / NOT STARTED.
  • Goal: Expose structured corroboration and correction.
  • Why: Complete free community participation.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; BUC-005; public representative observation reference.
  • Files/areas expected: app contribution UI; application/data adapters (area list, not a literal combined path).
  • Dependencies: P10-T06; all earlier phase gates.
  • Tests first: Self-confirm denial, idempotent retry, replaced price and private reason.
  • Implementation outline: Present conditions before confirmation; changed price creates observation.
  • Acceptance criteria: Clear status and no repeated vote amplification.
  • Validation commands: ./gradlew :application:test :app:testDebugUnitTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Confirming a stale/different condition accidentally.
  • Rollback/Recovery: Disable affected action; preserve submitted records for review.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T08 β€” Integrated offline and release checks

  • ID / priority / status: P10-T08 / MUST / NOT STARTED.
  • Goal: Prove upgrades and failure behavior on actual Android.
  • Why: Protect existing users at pilot rollout.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; TEST_STRATEGY; MIGRATION_PLAN.
  • Files/areas expected: Android instrumentation; contracts; privacy notices; release evidence (area list, not a literal combined path).
  • Dependencies: P10-T07; all earlier phase gates.
  • Tests first: Airplane mode, backend outage, wrong clock, schema-4 upgrade, old client/new API.
  • Implementation outline: Run full targeted/instrumented suites, accessibility/i18n and privacy policy review.
  • Acceptance criteria: No lost local data; public notices describe actual new collection.
  • Validation commands: ./gradlew test :app:lintDebug :app:assembleDebug :data:connectedDebugAndroidTest :app:connectedDebugAndroidTest. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Paper privacy policy or untested existing-device migration.
  • Rollback/Recovery: Stop rollout; disable community flag and use tested previous compatible release.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P10-T09 β€” Controlled community pilot

  • ID / priority / status: P10-T09 / MUST / NOT STARTED.
  • Goal: Release to limited cohort/city with measured quality.
  • Why: Validate useful data before monetization.
  • Inputs: docs/MIGRATION_PLAN.md, docs/user-business-logic.md; G10 test evidence; product metrics plan.
  • Files/areas expected: docs/product/pilot-results.md; runtime rollout configuration (area list, not a literal combined path).
  • Dependencies: P10-T08; all earlier phase gates.
  • Tests first: Rehearse flag off/rollback; verify aggregate metrics without tracking.
  • Implementation outline: Agree cohort/capacity/window, monitor freshness/disputes/cost and review outcomes.
  • Acceptance criteria: Pilot report states evidence, limits and next product decisions.
  • Validation commands: Run release smoke and compare monitored pilot metrics to acceptance targets. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Premature broad release or unsupported confidence claims.
  • Rollback/Recovery: Pause onboarding/contribution and keep ANP browsing available.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P11 β€” Optional hosted commercial services

Priority: LATER. Entry: Completed P10 pilot and explicit validated product scope.

Exit gate: G11: optional account/billing/sync specifications and implementations pass provider/ownership/conflict tests; no effect on free trust or existing local data. Each task is independently respecified before execution.

P11-T01 β€” Validate hosted offering

  • ID / priority / status: P11-T01 / LATER / NOT STARTED.
  • Goal: Choose one measured paid convenience use case.
  • Why: Avoid building speculative SaaS.
  • Inputs: docs/product/OPEN_SOURCE_BUSINESS.md, docs/MIGRATION_PLAN.md; Pilot findings; D09/D10.
  • Files/areas expected: docs/product/hosted-offering.md; cost model (area list, not a literal combined path).
  • Dependencies: Completed P10 pilot and explicit validated product scope; all earlier phase gates.
  • Tests first: Test demand assumptions and free-feature preservation checklist.
  • Implementation outline: Define entitlement/grace/export scope, data inventory and lawful basis.
  • Acceptance criteria: Concrete product acceptance, no paid trust feature.
  • Validation commands: Review product decision and updated unit-economics assumptions. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Building a large paid platform without demand.
  • Rollback/Recovery: Keep free product; discard unvalidated experiment.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P11-T02 β€” Optional account linking

  • ID / priority / status: P11-T02 / LATER / NOT STARTED.
  • Goal: Bind contributor ownership to a recoverable account.
  • Why: Offer device migration with proof.
  • Inputs: docs/product/OPEN_SOURCE_BUSINESS.md, docs/MIGRATION_PLAN.md; New account UC/security ADR required.
  • Files/areas expected: identity/account module and adapters; contracts (area list, not a literal combined path).
  • Dependencies: P11-T01; all earlier phase gates.
  • Tests first: Account takeover, stolen contributor ID, fresh reauth and key linking cases.
  • Implementation outline: Use established identity provider; prove current key and account; specify recovery.
  • Acceptance criteria: No unauthorized trust transfer; anonymous use continues.
  • Validation commands: Run account authz/recovery integration and E2E gates. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Recovery bypass becomes reputation theft.
  • Rollback/Recovery: Revoke link, audit incident and keep original contributor attribution safe.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P11-T03 β€” Server-verified entitlement

  • ID / priority / status: P11-T03 / LATER / NOT STARTED.
  • Goal: Translate purchase lifecycle to provider-neutral access.
  • Why: Never trust a premium boolean from client.
  • Inputs: docs/product/OPEN_SOURCE_BUSINESS.md, docs/MIGRATION_PLAN.md; New billing UC; current Play provider docs at execution.
  • Files/areas expected: subscription module; billing adapter; contracts (area list, not a literal combined path).
  • Dependencies: P11-T02; all earlier phase gates.
  • Tests first: Purchase replay/refund/revocation/notification duplication and stale state.
  • Implementation outline: Verify server-side, reconcile provider events, persist entitlement version.
  • Acceptance criteria: Payment independent from trust in regression tests.
  • Validation commands: Run provider sandbox verification and entitlement integration suite. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Fraudulent purchases or stale paid access.
  • Rollback/Recovery: Disable hosted entitlement grants; reconcile without changing community votes.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P11-T04 β€” Explicit favorites/settings sync

  • ID / priority / status: P11-T04 / LATER / NOT STARTED.
  • Goal: Synchronize first simple domains with conflicts.
  • Why: Avoid generic Room database replication.
  • Inputs: docs/product/OPEN_SOURCE_BUSINESS.md, docs/MIGRATION_PLAN.md; New sync UC and data inventory.
  • Files/areas expected: cloudsync module; Android sync adapter after spec (area list, not a literal combined path).
  • Dependencies: P11-T03; all earlier phase gates.
  • Tests first: Version conflict, two devices, tombstones, offline edit and subscription lapse.
  • Implementation outline: Version/ETag and explicit per-field merge/409 policy; scoped exports.
  • Acceptance criteria: No destructive replacement of local preferences.
  • Validation commands: Run cross-device sync conflict/offline E2E suite. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Silent last-write-wins data loss.
  • Rollback/Recovery: Disable sync; retain local state/export and audited server revisions.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

P11-T05 β€” Hosted backup and vehicle migration

  • ID / priority / status: P11-T05 / LATER / NOT STARTED.
  • Goal: Add paid convenience after simple sync proves reliable.
  • Why: Support device change without reducing local free use.
  • Inputs: docs/product/OPEN_SOURCE_BUSINESS.md, docs/MIGRATION_PLAN.md; New backup UC; pilot/sync evidence.
  • Files/areas expected: cloudsync module; Android opt-in backup (area list, not a literal combined path).
  • Dependencies: P11-T04; all earlier phase gates.
  • Tests first: Restore preview/conflict/cancel, local vehicle preservation, expired entitlement.
  • Implementation outline: Explicit consent and versioned domain export/import; exclude private signing keys.
  • Acceptance criteria: Three free local vehicles remain; restore is recoverable.
  • Validation commands: Run backup/restore and old/new Android compatibility suite. Where prose names a gate, introduce/document the exact executable command in this task before claiming completion.
  • Risks: Paid plan causes local loss or leaks keys.
  • Rollback/Recovery: Stop cloud writes; restore versioned user-selected snapshot.
  • Definition of done: DOD-1 plus this task's acceptance/validation evidence; update status/progress without claiming the next phase is complete.

Release-gate checklist G09

  • P01–P08 required phase PRs/fixes are integrated; G01…G08 and G01-FLOW evidence is linked to actual checks/commits/images/schema/config. Historical P01 direct commits are recorded without inventing retroactive PRs.
  • One immutable candidate SHA is selected after phase integration; full expected-result matrix is complete, including reconciliation of any reused specialized evidence. No missing/failed/skipped required release check or production deploy inferred from a phase merge.
  • Catalog import, identity, observation, media, validation, consensus, moderation and privacy flows run end to end.
  • Empty/upgrade migrations and duplicate/replay/concurrency cases pass.
  • Current OpenAPI and shared fixtures are frozen; legacy Android differences documented.
  • Existing Android regression baseline passes in a supported environment.
  • TLS/origin restriction, private storage, role/secret/dependency checks and critical/high finding closure verified.
  • Off-host encrypted backup restored into a new environment within accepted RPO/RTO; deletion ledger replayed.
  • Runtime retention/export/erasure and user notice/legal review are complete.
  • Load/fault/cache tests meet accepted capacity and freshness budgets.
  • Operator can deploy, monitor, moderate, revoke, rollback and restore using tested runbooks.
  • Release evidence signed off; P10-T01 is explicitly unblocked.