Project Progress Overview - Aaris-Baskaran/ENGR101-AVC-Team35 GitHub Wiki
Progress Overview:
June 3rd
Team meeting held to discuss project plan and resource installation
Installation issues resolved and draft plan constructed and roles chosen
Team member Marius Minnie absent from discussion due to communication issue
Project Start milestone commenced
June 4th
Communication issue with Marius Minnie resolved, team member informed of prior days discussions
Team meeting held to finalized project plan and member roles
Plan confirmed by all members then uploaded to GitHub as document by Project Manager
Outline of core code as pseudo code created and uploaded to GitHub by Program Architect
First version of core code created and uploaded to GitHub by Program Architect
Project Start milestone achieved on time
Core code milestone commenced
June 5th
Program Tester encountered technical issues trying to run the AVC Project; Issues resolved by Program Tester
Core code tested by Program Tester; two errors discovered when trying to ‘make’ the program
June 6th
Program Architect fixed errors discovered previous day, improved core code and suggested next steps to take
Program Tester checked core code found the code to function in all 10 runs attempted
Noted by Program Tester the while code does not work as required for actual functionality that the code works as currently intended
June 8th
Program Developer (Marius Minnie) fixed logic error occurring within code and added to code functionality
June 9th
Team meeting held to discuss project progress and determine what steps to take next
Meeting decided that core code was nearly ready however needed more time to create and test
Decision to move core code milestone due date to June 11th
Program Architect merged changes and formatted core code; basic test showed code in working state
After text chat discussion, decided to bring core code milestone due date to June 10th to allow for testing
June 10th
Core code testing determined that core code is suitably functional and we can proceed to next milestone
Core code milestone achieved 1 day after initial due date
June 11th
Team meeting held to discuss next steps; beginning on completion code
Outline of completion code as pseudo code created and uploaded to GitHub by Program Architect
First version of completion code created and uploaded to GitHub by Program Architect
Completion code milestone commenced 1 day after initial commencement date
June 15th
Core code final testing do by Program Tester; Program determined to be functioning well
Program Architect begun work on challenge code outline
Completion code milestone date not achieved
Challenge code milestone commenced
June 18th
Testing run by Program Tester yielded several errors
Team meeting held to discuss progress with regard to milestones and deadline
Program Architect has started and made good progress with challenge aspect of code
Program developer (Charles Erasmus) provided large contribution to completion code; Testing required
June 19th
Program Architect finished Completion and challenge code; working on MacOS
Program Tester having program crashing on windows
README updated with install and run instructions from Program Architect
Tried with multiple windows computers; program crashes
Many attempts at bug fixing / work around's for windows have yielded no successful results