Below is a table reflecting the progress of the project's schedule.
The milestone tasks below are associated with Sprints and associated issues which are labeled for it.
The milestone/task/issue being worked on will either have the WIP label associated with it, or a pull request created for it.
Any pending issues associated to a prior Sprint when that week's Sprint is finished, will have the current state/content of it copied to another issues, referencing the latest Spring, before being closed.
The Course Project's Projects tab will automatically handle the kanban workflow of the project. Below is a synopsis of the scheduling.
| Task (milestone linked) | Responsibility | Target Date | Status | New Expected Completion Date |
|---|---|---|---|---|
| SPRINT 1 | ALL | START DATE: Mar 28 | April 29 | |
| Yocto on Jetson Nano | Caleb Provost | Mar 29th | April 4 | |
| Define Communication IO | Zach Turner | Mar 29th | April 4 | |
| Get Nano demo running | Arpit Savarkar | Mar 27th | April 4 | |
| Arduino Setup Script post build | Mar 31 | N/A | ||
| SPRINT 2 | ALL | START DATE: April 5 | April 11 | |
| Update Arduino How-to | Arpit Savarkar | April 5 | April 11 | |
| Update Dockerfile to Absolute Path the Build Script | Caleb Provost | April 5 | April 11 | |
| Arduino BLE 33 Setup on Jetson | Arpit Savarkar | April 5 | April 11 | |
| Dockerize Arduino Build Environment | Caleb Provost | April 5 | April 11 | |
| Arduino Project Code in Docker | Arpit Savarkar | April 5 | April 11 | |
| Integrate Subsystems | Zach Turner | April 5 | April 11 | |
| Create Project's Yocto Layer | Caleb Provost | April 9 | April 11 | |
| SPRINT 3 | ALL | START DATE: April 12 | April 18 | |
| Create daemon for Jetson Nano | Zach Turner | April 12 | April 18 | |
| Test virtual wifi kernel module on Jetson {SIDE PROJECT} | Arpit Savarkar | April 12 | April 18 | |
| Resolve SD Card Image Creation | Caleb Provost | April 12 | April 18 | |
| Start to Finish Build Integration | Caleb Provost | April 12 | April 18 | |
| GPIO LED / I2C based Seven Segment Display to Jetson Nano | Arpit Savarkar | April 18 | April 18 | |
| API Setup and Response | Arpit Savarkar & Zach Turner | April 18 | April 18 | |
| Demo | ALL | START DATE: April 19 | April 24 | |
| Integrate yocto package for arduino_cli to meta-final-project | Arpit Savarkar & Caleb Provost | April 18 | April 22 | |
| All 4 One Script | Caleb Provost | April 18 | April 21 | |
| Add error checking to jetson serial application | Zach Turner | April 18 | April 22 | |
| Incorporate GPIO signal to UART server | Zach Turner | April 12 | April 18 | |
| Resolve SystemD Adaption Issue | ALL | April 18 | April 21 | |
| Integrate i2c-tools to yocto image | Arpit Savarkar | April 18 | April 21 |