<h1  style="text-align: center; color: green"> CAWCR-BoM ACCESS NWP Ngamai Migration Working Group</h1>
- 11am Wednesday 27th November , 10 East Meeting room
 
- Meeting 14, 13/11/2013
 - Meeting 13, 30/10/2013
 - Meeting 12, 16/10/2013
 - Meeting 11, 02/10/2013
 - Meeting 10, 18/09/2013
 - Meeting 9, 04/09/2013
 - Meeting 8, 28/08/2013
 - Meeting 7, 21/08/2013
 - Meeting 6, 14/08/2013
 - Meeting 5, 07/08/2013
 - Meeting 4, 31/07/2013
 - Meeting 3, 24/07/2013, v2
 - Meeting 2, 17/07/2013
 - Meeting 1, 10/07/2013
 - Initial pre-meeting notes
 
- Task List, updated after Meeting 10
 - Task List, updated after Meeting 9
 - 
Task List, updated after Meeting 5
- No new version after Meeting 6, just minor edit made to Item 41 wording
 
 
- Tilde ACCESS
 - MARS report - Robin, 29/08/2013
 - Apps locations - Robin, 04/09/2013
 - Bureau Project porting documentation S:\Head Office\Shared\NMOC\Ngamai Porting Project (BoM Internal only)
 - Access_NWP_Build_Procedures: Index page and documentation on procedures and build information of ACCESS NWP executables
 - RMS differences from a set of APS1 G runs
 - /apps documentation http://nmoc-svnop.bom.gov.au:8080/ (NMOC Wiki - BoM Internal only)
 - NMOC wiki pages on SVN repository and the new SMS being used on Ngamai -- http://wiki.bom.gov.au/foswiki/NMOC/SoftwareSystems/NgamaiPortIntro (Bom Internal only)
 
- This project covers migration of ACCESS-CAWCR-BoM (ESM) NWP systems from solar to ngamai, including reporting, documentation and resource planning.
 
- CAWCR: Michael Naughton, Asri Sulaiman, Robin Bowen, Ilia Bermous, Yi Xiao, Wenming Lu, Zhihong Li, Tan Le, Tim Pugh, Chris Tingwell, Martin Dix
 - NMOC: Jim Fraser, Joan Fernon, Ivor Blockley
 
- High level ngamai porting planning group
 - NMOC operational porting activity
 - /apps system team
 - nci/raijin access porting activity
 - Other porting groups ( poama, oceans, bluelink .... ).
 
- 
Contractual deadline for solar switch-off is 1st Nov 2013
 - 
Overrunning the deadline will have severe cost to BoM.
 - 
There is need for timely reporting to higher management, especially in relation to resourcing aspects, and risks of meeting time deadlines.
 - 
The key systems for solar switch off are operational systems; CAWCR research will also be expected to be moved off solar by the same time.
 
- [ 9/9/2013 ] azs: Cleaned this section, it have become pointless. Trac provide more accurate and convenient features if there is need to look at edit/update history.